Ruzzana Abu Bakar: Assalamualaikum and a very good evening, everyone. Welcome to TM's 2026 Third Quarter Analyst Briefing, hosted by our Managing Director and Group CEO, Dato' Amar Huzaimi, together with our Group CFO, Encik Ahmad Fairus. I'm Ruzzana from TM's Investor Relations, and if you are on our distribution list, you would have received a copy of the analyst briefing presentation by email. The slides are also available on our IR website under Quarterly Results and will be shown during this session. Before we begin, I would like to kindly remind everyone to keep your microphone muted. We will open the floor for a Q&A session after the presentation. Without further ado, I would like to hand over the briefing to Dato' Amar. Over to you, Dato'.

Amar Huzaimi: Thank you, Ruzzana. Assalamualaikum and a very good evening, everyone. Thank you for making the time to join us today. I will start with some of our key highlights, followed by an overview of our performance for the first nine months of the year, before handing the session over to our Group CFO, Encik Fairus, to elaborate on the financial and operational details. I will be back at the end of the presentation to share our outlook with some concluding remarks before we proceed to the Q&A session. You move to the second slide. Let me start with our key development for this quarter. We are pleased to have received several industry awards across the group recently, including recognition at the PC.com Readers' Choice Awards, BusinessToday Industry Awards, and PIKOM Digital Excellence Awards 2026.

Amar Huzaimi: This recognition underscored industry confidence in TM's solution, the quality of our services, and our capabilities to deliver digital solutions across the customer segments. Building on this momentum, we continue to strengthen our offerings to address evolving customer needs and to capture growth opportunities. One area where we are seeing encouraging traction is on cybersecurity, as businesses and government agencies becoming increasingly reliant on digital systems for their operations and critical services. To address this increasing need, we introduced our Unifi Business Shield Pro, an all-in-one cybersecurity solution tailored to SME customers.

Amar Huzaimi: On a broader scale, we also launched our TM Cyber Defence Centre, or better known as TM CYDEC, bringing together integrated cyber defense, threat intelligence, and round-the-clock monitoring to address more complex security requirements for enterprises and government customers. Since its launch, we have seen positive internal initial response with interest coming from customers in our integrated cybersecurity solutions.

Amar Huzaimi: Turning to AI and digital infrastructure readiness, I am pleased to say that KVDC Block 2 capacity is now fully contracted, with customer onboarding progressing. Within KVDC, we have a dedicated data hall to accommodate advanced liquid cooling solutions, providing flexibility to support higher density computing and AI workloads as customer requirements continue to evolve. Alongside our core data center colo business, we are progressively scaling our AI Foundry capabilities, including high-performance GPUs, largely to support internal requirements, local enterprises, and government for their AI computing workloads. While we observe encouraging demand for GPU as a service, we remain committed to strict compliance with applicable US export control governing advanced GPUs for future expansion. Overall, this development reflect the progress in delivering customer value, advancing our new core business, and developing the digital infrastructure to support our PWR2030 long-term growth strategy.

Amar Huzaimi: Nine months into 2026, TM has continued to deliver revenue growth despite an increasing competitive and evolving operating environment. Our group revenue grew by 3.3% year on year to MYR 8.9 billion, supported by positive contribution across all three customer segments. Growth was underpinned by sustained demand for connectivity, stronger adoption of convergence offerings, and increasing contribution from digital solutions. Our fixed broadband customer base remained resilient at approximately 3.22 million. New installation continued to remain healthy quarter on quarter. However, higher disconnection of circuit resulted in a modest reduction in our net adds. This partly reflects our proactive effort to manage persistent non-paying customers alongside the broader competitive market environment. Despite this, our subscriber base remained higher year on year, while broadband ARPU improved from MYR 130 to MYR 133 year on year, reflecting stronger take-up of higher value offerings.

Amar Huzaimi: TM's profitability was affected by several specific cost items, including the previous disclosed write-down of unutilized prepaid 5G MOCN capacity, alongside costs associated with Prihatin program and the FIFA World Cup 2026 broadcast rights during the period. Due to this, the group recorded EBIT of MYR 1.67 billion and PATAMI of MYR 1.18 billion, both lower compared to the corresponding period last year. Our bottom line was also impacted by a higher comparative base last year, which benefited from a one-off technology fund gain and a lower tax charges. Notwithstanding this, underlying performance continued to be resilient with EBIT and PATAMI year on year recording growth of 1.8% and 1% respectively. The details will be further deliberated later by Fairus. Our quarterly sequential performance is also encouraging, with reported EBIT increasing by 27% and PATAMI by 35% compared to the preceding quarter.

Amar Huzaimi: Following this, the board has declared a third interim dividend of 10 sen per share, or MYR 384 million, bringing cumulative dividend for the first nine months of 2026 to 23.5 sen per share, representing 76% of our reported PATAMI. This is very consistent with our dividend policy and reinforces our commitment to sustainable shareholder returns. As we are closing in the financial quarter of 2026, our immediate priority is to deliver on our full-year commitments and ensure our investment remain on track for future growth and returns. With that, let me hand over to Fairuz to take you through our financial and operational details. Fairuz?

Encik Ahmad Fairus: Thank you, Dato'. Assalamualaikum and very good evening, everyone. Let me begin with our underlying financial performance, which provides a clearer perspective on the group's operating result. As highlighted earlier, our reported profitability was affected by specific one-off item during the period. To provide a more meaningful year-on-year comparison, we have adjusted for the 5G MOCN capacity write-down, Prihatin-related costs, forex movements, and other identified non-recurring items. We have also deliberately excluded copper monetization from both current and comparative period. While it contributes to reported earnings, we believe excluding it provide a more prudent assessment of our recurring profitability without overstating the underlying performance of the business.

Encik Ahmad Fairus: After adjusting these items, our underlying EBIT increased by 1.8% year on year to MYR 1.82 billion, and similarly, underlying PATAMI grew by 1% year on year to MYR 1.29 billion after adjusting the identified items above, including one-off technology fund gain recognized last year. These results demonstrate the resilience of our core operations, with underlying profitability improving despite the challenging operating environment. Let us now take a closer look at each of customer segments, starting with B2C. On the B2C, revenue grew by 4.4% year on year to MYR 4.4 billion, supported by sustained broadband demand, stronger adoptions, convergence, and device bundling offerings.

Encik Ahmad Fairus: Our subscriber base remains relatively stable at 3.2 million. While new installations continue to increase during the quarter, higher disconnection resulted in negative net adds of circa 8,000 subscriber. As highlighted earlier, this partly reflects our proactive management of persistently non-paying customer accounts, alongside continued competitive pressure.

Encik Ahmad Fairus: Beyond managing subscriber quality, we are strengthening customer retention through targeted re-contracting, speed upgrades, and higher value bundle offerings. ARPU improved to MYR 133 from MYR 130 a year ago, while convergence increased to 38.7% from 37.5%, reflecting continued progress in enhancing customer value. We are also expanding our smart home solutions, including indoor and outdoor security cameras, to improve customer engagement and relationship with higher value service propositions. For MSMEs, Unifi Business continue to expand its digital solutions portfolio, supported by growing cloud storage adoptions and the introductions of Unifi Business Shield Pro, creating new opportunities beyond connectivity.

Encik Ahmad Fairus: Let us now move to B2B in the next slide. For B2B, revenue remained broadly stable at MYR 2 billion, growing at about 1% from the previous year. Quarterly revenue, however, was lower, reflecting the timing of project deliveries and higher one-off revenue in the comparative period.

Encik Ahmad Fairus: Connectivity remained our largest revenue contributors, supported by contract win-over, renewal, and upselling across both government and enterprise segments for the next generation services, including hybrid and pure SD-WAN offerings. Beyond connectivity, our core and customer projects continues to grow on a single-digit basis year-on-year, reflecting continued progress in diversifying our revenue streams. Commercial momentum also remained encouraging, with total contract value won reaching MYR 1.7 billion, up by 7% year-on-year, supporting future revenue visibility, and its contracts are progressively delivered. Our CAE, or Cloud Alpha Edge services, has now reached maximum utilization, while enterprise data center revenue has nearly doubled, reflecting increasing customer demand for colocation and digital infrastructure services. We are also seeing growing opportunities in enterprise mobility and digital solutions. Vision AI in digital solutions has been deployed on-premise use case, which provides a scalable 24/7 smart surveillance.

Encik Ahmad Fairus: B2B has also strengthened its position in cybersecurity, as evidenced by contract renewals in the defense sector during the quarter. Recently, TM launched TM Cyber Defence Centre, or TM CYDEC, allowing B2B customers to use a cyber fusion operating model combining connectivity, cloud, AI, and cybersecurity to help organizations to detect threats and respond faster. Quarterly, our B2B performance may fluctuate depending on the timing of contract awards and project milestone. Looking ahead, TM One will continue to expand our cloud, cybersecurity, smart services, and AI solution to accelerate the digital transformation of enterprises and the government. Let's go next to the page on C2C. As for C2C, the revenue has increased by 3.9% for the first nine months of 2026 to MYR 2.4 billion, with positive contributions from both domestic and international businesses, led by stronger international growth.

Encik Ahmad Fairus: Domestic business accounts almost equally split, with international marks more than half of TM Global's revenue, supported by HSBA bandwidth upgrades from wholesale customer alongside 5G mobile backhaul deployment. The accelerated 5G rollout has brought cumulative deployment now to more than 10,000 sites, contributing to year-on-year revenue growth. During the year, we have expanded additional transocean capacity to mobile operator through submarine cable between Peninsular Malaysia, Sabah, and Sarawak to accommodate growing 5G traffic requirements and increasing network utilization. On the international front, performance is sustained by growing demand for cross-border and international connectivity services. During the quarter, we have deployed new international data services, strengthening connectivity between Johor and Singapore to meet increasing regional traffic requirement. We have also activated high-capacity data center to data center, like for hyperscaler customers, enabling reliable and scalable interconnection across our network.

Encik Ahmad Fairus: Beyond connectivity, we are building the next layer of growth through data centers and AI infrastructure. C2C data center business recorded revenue growth over 20% year-on-year, supported by contribution from previously commissioned capacity. The fully committed expanded capacity at Iskandar Puteri Data Centre and Klang Valley Data Centre provides further visibility on future revenue contribution as customer onboarding progresses. TM Nxera phase 1 achieved its ready for service milestone in October. Phase 2 planning is now underway as interest and demand for data center services remain high. Moving on to our cost performance. Total cost increased by 6.9% year-on-year to MYR 7.51 billion, with the cost-to-revenue ratio rising by 2.9 percentage points to 84.4%. The higher cost base reflects both growth-related spending and non-recurring items recognized during the year.

Encik Ahmad Fairus: Around 40% of the year-on-year cost increase reflects the net impact of identified non-recurring and adjustment items. This includes 5G MOCN write-down, our forex, and Prihatin costs. Excluding these and other identified non-recurring items, our underlying cost-to-revenue ratio stood at 80.7% compared to 80.1% last year, providing a more comparable view of our cost performance. The increase is largely reflecting the change of revenue mix, particularly higher device bundle offerings, which carry associated direct costs. Looking at the key cost driver, direct costs increased by 12%, largely reflecting higher device bundle offerings and costs associated with our World Cup broadcast partnership, in line with our evolving revenue mix. Manpower costs increased by 4.8%, including expenses associated with our Prihatin initiative. As far as infrastructure and customer operation costs, it increased by 14%, primarily due to the previously disclosed write-down of unutilized prepaid 5G capacity.

Encik Ahmad Fairus: Excluding these items, the costs remain broadly flat year on year. On the operational costs, this cost item increased by 5.5%, partly reflecting higher receivable impairment charges against a prior year base that was benefit from net recovery following collections alongside other specific cost movement. Depreciation and amortization remain relatively stable, increasing by less than 1%. Let me now move to capital expenditure. Our capital investment for the first 9 months of 2026 stood at MYR 858 million, or circa 10% of our revenue. It is lower than the market guidance, and this is due to several factors. Firstly, there are several projects that have achieved lower cost base from optimized infrastructure design. Secondly, the international submarine cable investment amount have benefited from favorable foreign exchange movement during the period.

Encik Ahmad Fairus: Lastly, we have also took the initiative to phase certain investment into 2027 in line with project readiness and implementation timelines. Around 75% of our investment went to revenue-generating growth investment, including expanding fiber access and 5G backhaul, digital infrastructure, as well as deploying submarine cable system. Overall, more importantly, our strategic priorities remain unchanged. We continue to align capital deployment with business requirement and customer demand while ensuring that our investment delivers sustainable return. Dato' Amar will provide a further context on our full year CapEx outlook later. My last slide today on cash flow and financial position. Our operating cash flow stood at MYR 1.74 billion, lower than the corresponding period last year, primarily reflecting higher payments to supplier and employees, including Prihatin, as well as higher tax payment. These were partly offset by improved customer collections.

Encik Ahmad Fairus: Nevertheless, our free cash flow improved by 7% to approximately MYR 1.6 billion, largely reflecting lower capital expenditure during the period. We ended September with MYR 1.77 billion in cash and cash equivalents, higher than a year ago. Gross debt to EBITDA also improved to 0.9 times compared with 1.1 times last year, providing us additional balance sheet capacity to fund our strategic priorities while maintaining financial discipline. On returns, ROIC stood at 11.14%, remaining above our WACC of 8.87%, while the spread has narrowed compared to last year. This actually reflects the trailing 12-month calculation, which still captures the impact of one-off items that affected NOPLAT, our net operating less adjusted tax in the Q4 2025. We expect this impact to normalize as the items roll out during the measurement period.

Encik Ahmad Fairus: Looking ahead, as we progressively invest in new growth areas, our emphasis remains on disciplined capital allocation, ensuring that this investment generates sustainable returns above our cost capital. With that, let me hand back the session back to Dato' Amar. Over to you, Dato'.

Amar Huzaimi: Thank you, Fairus. Let me close with a few takeaways as we approach the year end. The group underlying performance in the last 9 months has grown positively as we continue progressing our strategic priorities. While the operating environment remains challenging, we are committed to sustaining the performance of our core businesses while selectively pursuing growth opportunities in digital infrastructure, AI, and digital solutions. Across our businesses, our priorities are clear. In B2C, we continue centering our convergence offering to deliver greater value to consumers and MSMEs. For B2B, we continue to expand our cloud, cybersecurity, smart services, and AI solutions to accelerate the digital transformation for enterprises and the government.

Amar Huzaimi: For C2C, we have pioneered and secured long-term demand from hyperscalers for our hyper-connected data centre and cross-border connectivity solutions, linking facilities in Malaysia with data centres in Singapore and major regional market through our vast terrestrial network and submarine cable ecosystems. Demand for data centre remains encouraging, with the Iskandar Puteri Data Centre Block 2 achieving 100% take-up, and TM Nxera initial 64 megawatt phase already contracted more than 70% capacity ahead of its operation. Together with the fully committed expanded capacity at KVDC, this development support our continued progress in commercializing digital infrastructure investments. Our full-year guidance for revenue and reported EBIT remain unchanged. We continue to expect revenue to grow at a low single-digit rate, while reported EBIT expected to remain at a similar level to financial year 2025.

Amar Huzaimi: We are revising our CapEx to revenue guidance to 16% to 18% from 18% to 20% previously, reflecting the lower spending as elaborated earlier by Fairus. Our third interim dividend of 10 cent per share, or MYR 384 million, is a testament to our continued commitment to enhancing value creation for our shareholders. We would like to also take opportunity to thank the government of Malaysia and MCMC for their continued trust in TM through the recent issuance of the notification of approval, or better known as NOA, for the SALAM submarine cable project. With decades of submarine cable experience, we look forward to strengthening connectivity between Peninsular Malaysia, Sabah, and Sarawak. These efforts advance our aspiration of becoming a digital powerhouse by 2030 and ensure TM remains central in orchestrating the digital ecosystem for Malaysia and the region.

Amar Huzaimi: As we close 2026, we remain focused on strengthening our competitiveness and profitability while upholding our commitment to sustainable shareholders returns. With that, we thank you for your time and attention. Let us proceed to the Q&A session.

Ruzzana Abu Bakar: Thank you, Dato' Amar and Encik Fairus. We will now open the floor for our Q&A session. If you would like to ask a question, please use the raise hand function, and we will take questions in the order shown. Yes, the first question comes from Foong. Please unmute your mic, Foong, and go ahead.

Foong Choong Chen: Hi, good afternoon, everyone. Thank you so much for hosting the call. Couple of questions from me. Firstly, in terms of the net loss in fixed broadband customers, what are you expecting going forward? Also, will we have to drop prices, do you think, to keep subscribers in this competitive landscape? As for the cleanup of non-paying accounts, has there been an increase in the bad debt provision in Q3? If so, how much was it, and are we expecting more going forward? That is the first question. Second question, can you quantify the one-off items in Q3 2026, as well as the year to date? In particular, the copper monetization and non-recurring items, that would be very useful. The third question I have, just wanted to seek some clarity here on one of the slides for TM One.

Foong Choong Chen: It was mentioned, new order intake, you have secured MYR 1.6 billion to MYR 1.7 billion. Does this include renewals? Also, what does that single-digit growth mean? Is it related to new orders secured this year being higher than last year, or are you saying that these new orders will then lead to single-digit revenue growth for TM One? Those are my three questions. Thank you.

Amar Huzaimi: Let me take on the TM One first, Foong. First of all, thank you very much for that question. For TM One, yes, it includes renewal. These are the contracts or the order that we have received for the year. The single-digit growth is comparatively to the year before. We are expecting encouraging order that we have received as compared to the previous year, and it does include renewal. I hope that clarifies. Let me take the first question, while Fairus, you work on the second one. On the broadband, we noted there is a drop in the net adds. As mentioned by Fairus earlier, the NI remains encouraging. Our NI remains encouraging, and there are steady track of trajectory towards growth there.

Amar Huzaimi: However, there are significant termination due especially on one, because of the non-paying customers and also the competitive landscape getting more stiffer nowadays. To your point whether dropping price is one of the strategy, no, it was never a strategy. Our strategy has always remained as a convergent portfolio play, and you can see it has ultimately provided a good benefit for us and draw some result recently as our ARPU is growing steadily. So, convergence portfolio is our way forward, and that is what enhancing our stickiness in terms of our broadband customers and also our ARPU growth. All right, you want to take on the second, on the copper?

Encik Ahmad Fairus: Hi, Foong. Thank you for the questions. Before we talk about the copper, you did ask on the one-off items. As I mentioned earlier, our reported EBIT or profitability includes couple of things. One is the disclosed 5G MOCN capacity write-down, about MYR 127 million. We also have our Prihatin initiative cost, as well as our forex and one small non-recurring cost that we incur during the period. As for copper, we have never disclosed how much is our total copper sales. But suffice to say, it is part of the recognition we have under the other operating income. So, entire is part of our operating income. Would that help actually with the clarification, Foong?

Foong Choong Chen: Yeah, Fairus, it helps. But is it possible to tell me what the non-recurring cost is related to? Maybe if you could come non-recurring cost with copper, right? In total, what is that number there for these two items? Non-recurring and the copper monetization one.

Encik Ahmad Fairus: I am not able to actually disclose how much is the total copper sales, yeah. But the non-recurring is just actually a very small item that we have. It is a non-recurring for this year. It will not recur. The idea here when we exclude the copper sales is actually to ensure that we provide the right recurring profitability for your assessment on Telekom Malaysia.

Foong Choong Chen: Okay, understood. Going back to the question on the fixed broadband side, on the non-paying accounts. Was there an increase in bad debt provision in Q3, and how much did it increase by? Is that the end of it, or are we expecting more termination of non-paying accounts going into subsequent quarters?

Encik Ahmad Fairus: Foong, on the impairment charges or the bad debt, it is actually at the normal trend, right. Except that actually last year, we were benefited from actually net receipt or good collections, and therefore we see a slightly higher compared to the same period, yeah. Otherwise, actually the trend is actually maintained as per what we have seen actually in the last few years.

Foong Choong Chen: Okay, understood. Thanks, Amar and Fairus.

Amar Huzaimi: Foong, you did ask about the outlook for the broadband, right?

Foong Choong Chen: Yes.

Amar Huzaimi: It is still too soon to tell, but what we can say for now, it is turning towards better.

Foong Choong Chen: Okay, got it. Thanks, Amar.

Ruzzana Abu Bakar: Okay, thank you, Foong. Okay, let's take another question coming from Ranjan. Ranjan, please unmute your microphone and proceed with your question.

Ranjan Sharma: Hi, good evening, and thank you for the presentation and opportunity. I have two questions, please. Can you help us with the EBITDA and underlying EBITDA? These numbers used to be disclosed, I think, up to like Q4, the Q1 of this year. If you can help us again with these numbers again, thank you. Second question is on your cash flows from operating activities. It is at MYR 1.7 billion for the first nine months, versus MYR 2.2 billion in the previous nine months, down about 22%. If you can help us understand what is driving these numbers. Thank you.

Encik Ahmad Fairus: Thanks, Ranjan, for the questions. On the underlying EBITDA, I cannot recall we actually provide that figure before. Nevertheless, I think there is nothing extraordinary in our depreciations. If you are actually looking from EBITDA, I think the underlying EBIT plus the depreciation would help actually in term of the underlying EBITDA. As with regard to our cash flow, yes, there are some reductions. If you could check, if you can refer to our Bursa announcement, the reductions was actually primarily from two items. One, because of our increase in our supplier and employee cost. This is pretty much from our Prihatin. That is actually number one. Number two is with regards to our tax payment. We have a lower tax payment last year, versus this year where we are following the normal corporate rate, yeah?

Encik Ahmad Fairus: The lower tax payment was benefited from actually our tax credit that we actually announced in 2024. Yeah. Sorry, 2020. Yeah, 2024. Correct.

Ranjan Sharma: Got it. Thank you so much.

Ruzzana Abu Bakar: Right. Thank you, Ranjan. Okay, next we have Koo. You can proceed with your question, Koo.

Khoo Zhen Ye: Hi. Yes, hi. Thank you, management, for the opportunity. I just have a couple of questions. I think I will ask one by one. I think the first question is on the data center. I mean, can I know what is the sort of the rates that you versus one year ago and the new contract that you are signing? Do you see a significant jump because of the demand? How can we quantify the data center sort of revenue contribution for your sort of C2C segment? That is my first question.

Amar Huzaimi: Okay, let me just try to understand the question. You are asking about the demand for the data center? Yes, as I mentioned earlier, we observe a strong demand for data centers. Competitively, largely for this year, it has been underpinned by our two upgrades that are made ready this year, our KVDC and IPDC. Of course, we saw an increasing of trend because this new capacity is available this year for us to at least secure and sell. Yeah.

Khoo Zhen Ye: Okay.

Amar Huzaimi: Yeah.

Khoo Zhen Ye: How are the rates? I mean, the kind of the charge that you are charging to your hyperscaler customers?

Amar Huzaimi: We charge our hyperscalers. Of course, we do not discuss our rates. The rate will be depending on the volume and tenure that they subscribe with us. What I can say, our rate has been contributing healthily to our top line and also the bottom line. That is why you can see the growth of TM Global largely also been contributed by data centre too.

Khoo Zhen Ye: Okay. How big is the TM Global in terms of total revenue contribution from DC? Could you give us a

Amar Huzaimi: We do not disclose the actual breakdown, Ku. Yes, it does help in terms of growing our top line, especially because data centre is one of our key growth areas with regard to the new digital infrastructure that we are investing in.

Khoo Zhen Ye: Okay, got it. I think I want to follow on the TM Nxera. You mentioned the first 64 megawatt, more than 70% is already contracted, means you are already running it, is it? The utilization more than 70%.

Amar Huzaimi: The onboarding is ongoing because the 64 megawatt will be ready in phases, expected to be fully ready by Q1 end next year. However, we have received almost 70% order that we have received. Sorry, 70% of the capacity that is going to be ready next year is already being taken up.

Khoo Zhen Ye: Okay, already been taken up and will ramp up fully until end of Q1.

Amar Huzaimi: Yeah, it will be deployed gradually by next year as and when the capacity is being made available, Ku.

Khoo Zhen Ye: Okay, understood.

Amar Huzaimi: I hope I further clarified that statement.

Khoo Zhen Ye: Understood. You mentioned about the expansion on the second 64 megawatt. You mentioned about slow server lead time. Is it because of due to capacity constraint or do you need some additional maybe export licenses or clarification?

Amar Huzaimi: Come again? I do not quite follow the question. Can you kindly repeat the question again?

Khoo Zhen Ye: Hello? Hi, can you hear me?

Amar Huzaimi: Yeah, yeah.

Khoo Zhen Ye: All right. My second question is on the expansion of the second 64 megawatt of TM Nxera. I think in the slides, you mentioned about long server lead time. So, I am asking, when would the second 64 megawatt would be expanded? The reason behind the long server lead time, is it because of the long lead times or is it do you need to do additional compliance checks or additional export licenses for the GPUs to be set up in your TM Nxera?

Encik Ahmad Fairus: Maybe, Ku, Fairus, let me try to explain here.

Khoo Zhen Ye: Okay

Encik Ahmad Fairus: There are two parts of the things that we are discussing. One, with regards to the planning for Nxera phase 2. It is a two different story with regards to the facings or the server. For the Nxera, it is more of actually the data center for colo business. The one that you mentioned with regards to the CapEx, the slow server, is our purchase or procurement with regards to our CapEx. These are two different thing, if I can clarify that.

Khoo Zhen Ye: Okay. You mean in terms of CapEx to procure the GPUs that you-

Encik Ahmad Fairus: Yeah. Because TM Nxera is actually a joint venture equity account. So, we do not consolidate CapEx. The one that we discussed on the slow server and all that is actually with regards to our total CapEx spending. With regards to TM Nxera, the phase 2 is already under planning. Yeah.

Khoo Zhen Ye: Okay, got it. Could we get a mix of the customer mix between the US and non-US for your TM Nxera?

Amar Huzaimi: Well, we do not disclose our customer mix. However, I can safely say for Telekom Malaysia, largely our colo is constituted by our Western block. Of course, there are part of these Eastern customers also with us, but we are strictly complying to the US guidelines, the trade guidelines, for sure.

Khoo Zhen Ye: Okay. All right. Thank you very much. Terima kasih banyak. Terima kasih.

Ruzzana Abu Bakar: All right. Thank you, Ku. Up next, Prem. Go ahead, Prem.

Prem Jearajasingam: Hi. Thank you for the opportunity. A few questions from me. First one, help me understand this one. Your reported EBIT up to nine months is MYR 1.7 billion. The underlying is about MYR 1.8 billion according to your slides. But your guidance of MYR 2 billion EBIT still stands. Could you help us understand what you expect in large cost in Q4 that would take us down to MYR 2 billion, given your current run rate's about MYR 600 million a quarter? That's the first question. Maybe you answer that first.

Encik Ahmad Fairus: Thanks, Prem. I think it's very obvious, actually, the reported versus actually the underlying, and we have outlined. As far as Q4, it's still fluctuating. As usual, we are-

Amar Huzaimi: We have not done. I mean, what happened in last quarter, last year, Q4, we received a lot of applications with regards to our Prihatin initiative. This is what we cannot anticipate still, right? It is not something that we advocate. It is based on actually the request coming from our people. At this juncture, I think it is safe to say, actually, we will maintain our guidance. That is how I will see it, actually. I wouldn't be able to speculate because this is all based on applications, and we will process it accordingly.

Prem Jearajasingam: Okay, perfect. It means, because I think Q4 last year, we had something like MYR 300 plus million in Prihatin.

Amar Huzaimi: Exactly.

Prem Jearajasingam: Barring another MYR 300 million in the Q4, we should be better than the MYR 2 billion, but in the matter of prudence, we will keep that guidance as it is. Is that a fair comment?

Amar Huzaimi: Very fair, actually, Prem.

Prem Jearajasingam: Okay, perfect. Now, next question. With regard to this Prihatin, just coming back to Ranjan's point earlier, there is a big drop-off in the operating cash flows, and you mentioned Prihatin in there. Would it be safe to assume that while you took the provision of MYR 300 million in Q4 FY25, the actual payments would have happened in FY26, and that would have contributed to this cash flow difference? Is that a fair comment?

Amar Huzaimi: The answer is yes, because we do not. I think from actually the accounting, we will recognize the provision upon acceptance, but payment is in progress subject to regulatory clearance and few other things that we have to sort out from administrative perspective, procedure. Yeah.

Prem Jearajasingam: Okay. Coming back to this, because AI DCs have gone from being a good word to a very bad word in the last week, how significant are AI workloads within your overall DC capacity? Would you put it at below 10% or above 10%, as simple as that?

Amar Huzaimi: Let me take that question, Prem. As I mentioned earlier, largely our capacity in data centers today are supporting CPUs for cloud services.

Prem Jearajasingam: Yes.

Amar Huzaimi: We are deploying GPUs, as I mentioned earlier, but that one is based on demand-led, right? That is to support our own internal requirement, our local enterprise requirements, and our current government requirements too, running their own AI workloads, yeah? As and when there are future demands of GPU, we will strictly comply to the new ruling which currently announced by the government of the US.

Prem Jearajasingam: Perfect. Thank you very much.

Amar Huzaimi: Not much exposure there, yeah. Thank you.

Prem Jearajasingam: Yeah. Thank you.

Ruzzana Abu Bakar: All right. Thank you, Prem. We have another question from Ranjan. Go ahead, Ranjan.

Ranjan Sharma: Hi. Sorry, I forgot to lower my hand. You can go to the next person. Sorry.

Ruzzana Abu Bakar: All right. Okay, Ranjan. Okay. How about you, Foong? You are raising your hand again.

Foong Choong Chen: Yeah. Thanks. Thanks. Got two more questions. Firstly, on the Prihatin cost, right? I appreciate you don't disclose the exact amount, but can you share if year to date, right, the Prihatin cost was higher or lower than last year? In terms of the application for Prihatin, right, so far up to the end of November, what are you seeing in terms of the rate of application? That's the first question. Second question, can you share a bit more color on the SALAM submarine cable project? Are you expecting to receive any government grants for that project, or will it be fully funded by TM? In the Bursa announcement, I note that TM state it is still reviewing the official terms before formally accepting the role. Does that mean that the terms are still open for negotiation?

Foong Choong Chen: How should we think about earnings contribution from the SALAM project once it is a commercial launch? Those are my two questions. Thank you.

Amar Huzaimi: Let me take up the Prihatin cost. It is safe to assume that the Prihatin cost for this year will not be as extensive as last year. As we mentioned at the early of the year, we do not anticipate a large take-up as per last year due to the current environment that we are now facing today. I hope that will clarify, Foong. It will not be as high as last year.

Foong Choong Chen: Okay. Okay, got it.

Amar Huzaimi: All right. With respect to the SALAM cable, yes, it will be a USP project by the MCMC, as per announced by MCMC too. So it will be fully funded by the government of Malaysia for the SALAM project. The terms, as you were mentioning, we were given 14 working days for us to review the terms and condition. Of course, we are now in the midst of negotiating. There will not be a major negotiation of the term and condition largely, but it is more on the timing of the cash in terms of what is the process on the claims, et cetera. But it will not be on the fundamental of that particular project concept. So I hope that will clarify.

Foong Choong Chen: Ahmad, you mean that MYR 2.7 billion fully funded by the government and TM will pay first, is it, and then claw it back from your USP contribution, is it, on a daily basis? Is that what will happen?

Amar Huzaimi: Sorry, first of all, the MYR 2.7 billion, yes, is going to be funded by the government, and we will be claiming, largely it is more back-to-back arrangement between our partner and also MCMC.

Foong Choong Chen: Okay. The SALAM submarine cable will be owned by the government, or will it be owned by TM?

Amar Huzaimi: It will be owned by TM.

Foong Choong Chen: Despite the fact that the government is paying for it?

Amar Huzaimi: Yes. We will have to take care in terms of maintaining and operating the submarine cable system once ready, expected by 2030. Of course, for about 25 years. From that, we will be able to monetize that infrastructure as well.

Foong Choong Chen: Okay, understood. That would mean, MYR 2.7 billion over three to four years would mean about maybe about MYR 800, MYR 900 million of CapEx. That will not go into your CapEx for next year or in the following years, into your CapEx guidance, right? Just to clarify.

Amar Huzaimi: Yeah, just let Fairus clarify that for you. Thank you.

Encik Ahmad Fairus: Thanks, Poh. Typically, government-funded project, it will not be part of our CapEx, but we still actually continue to monitor and track the expenditure.

Foong Choong Chen: Okay. Sounds like a good deal. Thank you so much.

Amar Huzaimi: Thank you.

Ruzzana Abu Bakar: All right. We have another question from Kylie. Kylie, can you unmute your microphone?

Kylie Chan Sze Zan: Hi, everyone. Thanks for the briefing. Just two questions. For your subscriber cleanup exercise on Unifi, how long will this persist? Secondly, for your DC-to-DC connectivity business, could you reveal your exposure to China-based clients? Just these two from me.

Amar Huzaimi: Let me clarify again. It is not a cleanup exercise. It is just that the trend of the non-paying increase in that particular quarter, as I mentioned earlier, it is still too early to say, but we observe a better trending in the subsequent quarter. So I hope that will clarify with respect to the broadband trending, yeah? So it is not a cleanup process. It is a trend that the non-payment happens to be high this year, for example, yeah? With your question on the DC-to-DC connectivity, we are very clear, largely the requirement coming from both, from the eastern side, on large hyperscalers like ByteDance, Alibaba, Tencent, and some of the Chinese carrier too. But we also serve our hyperscalers from the western part, like Microsoft, Google, Meta, and also Oracle, yeah? And we are specifically complying to the regulation.

Amar Huzaimi: For example, the equipment is serving our Western hyperscalers are not Chinese equipment. So we are very strict in terms of providing that or complying to that particular rule. I hope that will clear the air with respect to the connectivity that we provide to our hyperscalers, be it from China or Eastern and also the Western bloc.

Kylie Chan Sze Zan: All right. Thanks so much. Just to follow up on the second question. Can I say that it is largely quite balanced between East and West for these hyperscalers?

Amar Huzaimi: You can put it that way. Yeah, almost balanced, yeah.

Kylie Chan Sze Zan: All right. Okay, thank you.

Amar Huzaimi: Both are equally large hyperscalers from both side of the Eastern and also Western bloc.

Kylie Chan Sze Zan: Okay, thank you.

Amar Huzaimi: No worries. Thank you.

Ruzzana Abu Bakar: All right. Thank you, Kylie. Is there any more questions? We have few more minutes. All right. Since there is no more questions, thank you, everyone, for spending your time with us today. If you have any further questions, please do not hesitate to contact the IR team. Any parting words, Chief? No? Okay. Thank you so much.

Amar Huzaimi: Thank you very much. Thank you very much.

Q3 2026 Telekom Malaysia Bhd Earnings Call

Demo

TM

Earnings

Q3 2026 Telekom Malaysia Bhd Earnings Call

TM

Wednesday, November 25th, 2026 at 9:30 AM

Transcript

No Transcript Available

No transcript data is available for this event yet. Transcripts typically become available shortly after an earnings call ends.

Want AI-powered analysis? Try AllMind →