Q2 2026 Orsted AS Earnings Call
Operator: Ladies and gentlemen, welcome to the Ørsted Interim Report for the Q2 2026 conference call. I am Hillary, the conference call operator. I would like to remind you that all participants will be in listen-only mode and the conference is being recorded. The presentation will be followed by a Q&A session. You can register for questions at any time by pressing Star and One on your telephone. For operator assistance, please press Star and Zero. The conference must not be recorded for publication or broadcast. At this time, it is my pleasure to hand over to Group President and CEO, Rasmus Errboe, and CFO, Trond Westlie. Please go ahead.
Operator: Ladies and gentlemen, welcome to the Ørsted Interim Report for the Q2 2026 conference call. I am Hillary, the conference call operator. I would like to remind you that all participants will be in listen-only mode and the conference is being recorded. The presentation will be followed by a Q&A session. You can register for questions at any time by pressing Star and One on your telephone. For operator assistance, please press Star and Zero. The conference must not be recorded for publication or broadcast. At this time, it is my pleasure to hand over to Group President and CEO, Rasmus Errboe, and CFO, Trond Westlie. Please go ahead.
Speaker #1: Ladies and gentlemen, welcome to the Ørsted Interim Report for the second quarter of 2026 conference call. I am Heli, the Chorus Call operator. I would like to remind you that all participants will be in listen-only mode, and the conference is being recorded.
Speaker #1: The presentation will be followed by a Q&A session. You can register for questions at any time by pressing star and 1 on your telephone.
Speaker #1: For operator assistance, please press star and 0. The conference must not be recorded for publication or broadcast. At this time, it's my pleasure to hand over to Group President and CEO, Rasmus Errboe, and CFO, Trond Westlie.
Speaker #1: Please go ahead.
Speaker #2: Thank you very much. Hello everyone, and thank you for joining today's call. The first half of 2026 has once again reminded us how quickly geopolitical tensions can impact global energy markets.
Rasmus Errboe: Thank you very much. Hello, everyone, and thank you for joining today's call. The H1 2026 has once again reminded us how quickly geopolitical tensions can impact global energy markets. The volatility has underlined the importance of European energy independence, which cannot be taken for granted. These chances also represent an opportunity for Europe to strengthen competitiveness for businesses through electrification and lowering of energy costs. An opportunity to ramp up production of homegrown, affordable, and reliable energy, so global shocks to energy markets do not limit prosperity. Renewable energy is central to this necessary transition. As a reminder, each of the recent 10 years have been the 10 warmest years ever recorded on Earth. Combined with wildfires across Southern Europe this summer, this obviously further underscores the need for a rapid acceleration of the energy transition.
Rasmus Errboe: Thank you very much. Hello, everyone, and thank you for joining today's call. The H1 2026 has once again reminded us how quickly geopolitical tensions can impact global energy markets. The volatility has underlined the importance of European energy independence, which cannot be taken for granted. These chances also represent an opportunity for Europe to strengthen competitiveness for businesses through electrification and lowering of energy costs. An opportunity to ramp up production of homegrown, affordable, and reliable energy, so global shocks to energy markets do not limit prosperity. Renewable energy is central to this necessary transition. As a reminder, each of the recent 10 years have been the 10 warmest years ever recorded on Earth. Combined with wildfires across Southern Europe this summer, this obviously further underscores the need for a rapid acceleration of the energy transition.
Speaker #2: The volatility has underlined the importance of European energy independence, which cannot be taken for granted. But these challenges also represent an opportunity for Europe to strengthen competitiveness for businesses through electrification and lowering of energy costs.
Speaker #2: An opportunity to ramp up production of homegrown, affordable, and reliable energy so global shocks to energy markets do not limit prosperity. Renewable energy is central to this necessary transition.
Speaker #2: And as a reminder, each of the recent 10 years have been the 10 warmest years ever recorded on Earth, and combined with wildfires across Southern Europe this summer, this obviously further underscores the need for a rapid acceleration of the energy transition.
Speaker #2: To improve European sovereignty and resilience, increased investments into renewable energy is central and necessary. With the right actions now, offshore wind can provide several significant benefits for Europe and the energy transition as a whole.
Rasmus Errboe: To improve European sovereignty and resilience, increased investments into renewable energy is central and necessary. With the right actions now, offshore wind can provide several significant benefits for Europe and the energy transition as a whole. As we highlighted in our recent paper, The Real Value of Offshore Wind, the build-out of renewables with offshore wind as a significant component can reduce annual fossil fuel imports by more than 30% of the current import need. Further, these investments can reduce total European electricity system costs by up to 30% by 2040, as the integration costs of solar and wind are marginal compared to the large savings from reduced use of fossil fuels in power generation.
Rasmus Errboe: To improve European sovereignty and resilience, increased investments into renewable energy is central and necessary. With the right actions now, offshore wind can provide several significant benefits for Europe and the energy transition as a whole. As we highlighted in our recent paper, The Real Value of Offshore Wind, the build-out of renewables with offshore wind as a significant component can reduce annual fossil fuel imports by more than 30% of the current import need. Further, these investments can reduce total European electricity system costs by up to 30% by 2040, as the integration costs of solar and wind are marginal compared to the large savings from reduced use of fossil fuels in power generation.
Speaker #2: As we highlighted in our recent paper, the real value of offshore wind, the build-out of renewables with offshore wind as a significant component, can reduce annual fossil fuel imports by more than 30% of the current import need.
Speaker #2: Further, these investments can reduce total European electricity system costs by up to 30% by 2040. As the integration costs of solar and wind are marginal compared to the large savings from reduced use of fossil fuels in power generation.
Speaker #2: Finally, the paper shows that an investment level into offshore wind in line with the ambitions outlined in the Hamburg Offshore Wind Investment Pack can cut annual carbon emissions in Europe by 20% compared to 2023 levels corresponding to 550 million tons of CO2.
Rasmus Errboe: Finally, the paper shows that an investment level into offshore wind in line with the ambitions outlined in the Hamburg Offshore Wind Investment Pact can cut annual carbon emissions in Europe by 20% compared to 2023 levels, corresponding to 550 million tons of CO2. When we assess the outlook for offshore wind, we see several positive signs for our industry, and we remain optimistic about the prospects for the sector. In the short term, there are several attractive offshore wind opportunities where the regulatory frameworks have improved and contributed to strengthening the investment certainty for future projects. We have seen improvements in the framework across several markets in Europe, including Denmark, UK, and Poland. Most recently, the budget for the upcoming CFD tender round in the Netherlands was also increased.
Rasmus Errboe: Finally, the paper shows that an investment level into offshore wind in line with the ambitions outlined in the Hamburg Offshore Wind Investment Pact can cut annual carbon emissions in Europe by 20% compared to 2023 levels, corresponding to 550 million tons of CO2. When we assess the outlook for offshore wind, we see several positive signs for our industry, and we remain optimistic about the prospects for the sector. In the short term, there are several attractive offshore wind opportunities where the regulatory frameworks have improved and contributed to strengthening the investment certainty for future projects. We have seen improvements in the framework across several markets in Europe, including Denmark, UK, and Poland. Most recently, the budget for the upcoming CFD tender round in the Netherlands was also increased.
Speaker #2: When we assess the outlook for offshore wind, we see several positive signs for our industry, and we remain optimistic about the prospects for the sector.
Speaker #2: In the short term, there are several attractive offshore wind opportunities, where the regulatory frameworks have improved and contributed to strengthening the investment certainty for future projects.
Speaker #2: We have seen improvements in the framework across several markets in Europe, including Denmark, the UK, and Poland. Most recently, the budget for the upcoming CfD tender round in the Netherlands was also increased.
Speaker #2: Our solid progress across our major construction portfolio where we continue to progress all projects on time and on budget should also give policymakers another key and other key stakeholders increased confidence that the offshore wind industry can in fact deliver renewable energy at massive scale as long as sufficient volumes are tendered out on a recurring basis with the right frameworks.
Rasmus Errboe: Our solid progress across our major construction portfolio, where we continue to progress all projects on time and on budget, should also give policymakers and other key stakeholders increased confidence that the offshore wind industry can in fact deliver renewable energy at massive scale as long as sufficient volumes are tendered out on a recurring basis with the right frameworks. In the mid to long term, the outlook for offshore wind, particularly in Europe, also remains strong. This is underlined by the 300 gigawatt offshore wind build-out target agreed in Hamburg in January 2026. Compared to 2024 levels, this build-out in the North Sea would amount to an increase in the capacity of European offshore wind by a factor of eight, representing a significant growth opportunity for the industry. At the European political level, the need for an acceleration of the energy transition is also recognized.
Rasmus Errboe: Our solid progress across our major construction portfolio, where we continue to progress all projects on time and on budget, should also give policymakers and other key stakeholders increased confidence that the offshore wind industry can in fact deliver renewable energy at massive scale as long as sufficient volumes are tendered out on a recurring basis with the right frameworks. In the mid to long term, the outlook for offshore wind, particularly in Europe, also remains strong. This is underlined by the 300 gigawatt offshore wind build-out target agreed in Hamburg in January 2026. Compared to 2024 levels, this build-out in the North Sea would amount to an increase in the capacity of European offshore wind by a factor of eight, representing a significant growth opportunity for the industry. At the European political level, the need for an acceleration of the energy transition is also recognized.
Speaker #2: In the mid to long term, the outlook for offshore wind, particularly in Europe, also remains strong. This is underlined by the 300 gigawatt offshore wind build-out target, agreed in Hamburg in January 2026.
Speaker #2: Compared to 2024 levels, this build-out in the North Sea would amount to an increase in the capacity of European offshore wind by a factor of eight, representing a significant growth opportunity for the industry.
Speaker #2: And at the European political level, the need for an acceleration of the energy transition is also recognized. The recently proposed review of the EU Emissions Trading System reflects the EU's continued reliance on a rules-based carbon market, as it's central climate policy instrument.
Rasmus Errboe: The recently proposed review of the EU Emissions Trading System reflects the EU's continued reliance on a rules-based carbon market as its central climate policy instrument. At the same time, the Electrification Action Plan and the proposal on electricity network charges reinforces the Commission's focus on accelerating electrification across sectors to strengthen Europe's competitiveness, energy security, and decarbonization, highlighting the need for continued investments in renewable generation, stronger electricity grids, and greater system flexibility. We are encouraged with the continued positive signs for our industry, and we will continue to be a close partner to governments and industry peers to provide solutions for the acceleration of offshore wind.
Rasmus Errboe: The recently proposed review of the EU Emissions Trading System reflects the EU's continued reliance on a rules-based carbon market as its central climate policy instrument. At the same time, the Electrification Action Plan and the proposal on electricity network charges reinforces the Commission's focus on accelerating electrification across sectors to strengthen Europe's competitiveness, energy security, and decarbonization, highlighting the need for continued investments in renewable generation, stronger electricity grids, and greater system flexibility. We are encouraged with the continued positive signs for our industry, and we will continue to be a close partner to governments and industry peers to provide solutions for the acceleration of offshore wind.
Speaker #2: At the same time, the electrification action plan and the proposal on electricity network charges reinforces the Commission's focus on accelerating electrification across sectors to strengthen Europe's competitiveness.
Speaker #2: Energy security and decarbonization. Highlighting the need for continued investments in renewable generation, stronger electricity grids, and greater system flexibility. We are encouraged with the continued positive signs for our industry, and we will continue to be a close partner to governments and industry peers to provide solutions for the acceleration of offshore wind.
Speaker #2: By continuing to deliver on our business plan, we will become a more focused competitive and stronger company, and we will assess the upcoming tenders and auctions with a disciplined approach to capital allocation, as we are ready to pursue the most value-creating opportunities to remain the global leader in offshore wind.
Rasmus Errboe: By continuing to deliver on our business plan, we will become a more focused, competitive, and stronger company, and we will assess the upcoming tenders and auctions with a disciplined approach to capital allocation as we are ready to pursue the most value-creating opportunities to remain the global leader in offshore wind. Let's continue to slide 5 and an update on the strategic priorities and our operational performance. Our first priority is to strengthen our capital structure, and with the closing of the divestment of the European onshore business in April, we have made further progress on this. Also, the divestment of a 50/50% stake in our Greater Changhua 2 project is still expected to close later this year, following the commissioning of Greater Changhua 2B and 4. Lastly, our continued strong business performance is driving our solid earnings generation, which is supportive of our financial foundation.
Rasmus Errboe: By continuing to deliver on our business plan, we will become a more focused, competitive, and stronger company, and we will assess the upcoming tenders and auctions with a disciplined approach to capital allocation as we are ready to pursue the most value-creating opportunities to remain the global leader in offshore wind. Let's continue to slide 5 and an update on the strategic priorities and our operational performance. Our first priority is to strengthen our capital structure, and with the closing of the divestment of the European onshore business in April, we have made further progress on this. Also, the divestment of a 50/50% stake in our Greater Changhua 2 project is still expected to close later this year, following the commissioning of Greater Changhua 2B and 4. Lastly, our continued strong business performance is driving our solid earnings generation, which is supportive of our financial foundation.
Speaker #2: Let's continue to slide 5, and an update on the strategic priorities and our operational performance. Our first priority is to strengthen our capital structure.
Speaker #2: And with the closing of the divestment of the European onshore business in April, we have made further progress on this. Also, the divestment of a 50/50% stake in our Greater Changhua 2 project is still expected to close later this year.
Speaker #2: Following the commissioning of Greater Chiang Mai 2B and 4. Lastly, our continued strong business performance is driving our solid earnings generation, which is supportive of our financial foundation.
Speaker #2: With the measures we have taken during the last 18 months, we have the necessary robustness to pursue new value-creating opportunities within offshore wind, while also reinstating a dividend payout in line with our previous commitments.
Rasmus Errboe: With the measures we have taken during the last 18 months, we have the necessary robustness to pursue new value-creating opportunities within offshore wind, while also reinstating a dividend payout in line with our previous commitments. Trond will cover the details of the dividend policy later in the presentation. Our second priority is to deliver on our 8.1-gigawatt offshore wind construction portfolio, where we expect to commission three projects with a total capacity of 2.5 gigawatt this year. We have achieved significant progress during the quarter and are progressing according to schedule and budget. I will shortly go through the construction progress in more detail. Our third priority is a focused and disciplined approach to capital allocation. As we look ahead for new offshore wind opportunities in Europe and select markets in APAC, we will maintain our disciplined approach with a focus on value.
Rasmus Errboe: With the measures we have taken during the last 18 months, we have the necessary robustness to pursue new value-creating opportunities within offshore wind, while also reinstating a dividend payout in line with our previous commitments. Trond will cover the details of the dividend policy later in the presentation. Our second priority is to deliver on our 8.1-gigawatt offshore wind construction portfolio, where we expect to commission three projects with a total capacity of 2.5 gigawatt this year. We have achieved significant progress during the quarter and are progressing according to schedule and budget. I will shortly go through the construction progress in more detail. Our third priority is a focused and disciplined approach to capital allocation. As we look ahead for new offshore wind opportunities in Europe and select markets in APAC, we will maintain our disciplined approach with a focus on value.
Speaker #2: Trond will cover the details of the dividend policy later in the presentation. Our second priority is to deliver on our 8.1-gigawatt offshore wind construction portfolio, where we expect to commission three projects with a total capacity of 2.5 gigawatts this year.
Speaker #2: We have achieved significant progress during the quarter and are progressing according to schedule and budget. I will shortly go through the construction progress in more detail.
Speaker #2: Our third priority is a focused and disciplined approach to capital allocation. As we look ahead for new offshore wind opportunities in Europe and select markets in APAC, we will maintain our disciplined approach with a focus on value.
Speaker #2: Our fourth priority is to improve our competitiveness, and we are continuing to progress as planned on numerous measures across our organization to achieve a stronger and more competitive Ørsted.
Rasmus Errboe: Our fourth priority is to improve our competitiveness, and we are continuing to progress as planned on numerous measures across our organization to achieve a stronger and more competitive Ørsted. As part of improving our competitiveness, we recently outlined our decarbonization efforts towards 2040 in our The Next Zero paper, which describes how we, with our partners, will work to achieve cost-effective reductions of key emissions hotspots across the offshore wind value chain. Reducing value chain emissions is essential from a climate impact perspective and will improve our value proposition in future offshore wind auctions. Turning to the operational highlights of the H1 of the year, I am very satisfied with our operational performance. Our EBITDA, excluding new partnerships and cancellation fees, amounted to DKK 15 billion, which is an increase of more than DKK 1 billion compared to H1 2025.
Rasmus Errboe: Our fourth priority is to improve our competitiveness, and we are continuing to progress as planned on numerous measures across our organization to achieve a stronger and more competitive Ørsted. As part of improving our competitiveness, we recently outlined our decarbonization efforts towards 2040 in our The Next Zero paper, which describes how we, with our partners, will work to achieve cost-effective reductions of key emissions hotspots across the offshore wind value chain. Reducing value chain emissions is essential from a climate impact perspective and will improve our value proposition in future offshore wind auctions. Turning to the operational highlights of the H1 of the year, I am very satisfied with our operational performance. Our EBITDA, excluding new partnerships and cancellation fees, amounted to DKK 15 billion, which is an increase of more than DKK 1 billion compared to H1 2025.
Speaker #2: As part of improving our competitiveness, we recently outlined our decarbonization efforts toward 2040 in our next ZERO paper, which describes how we, with our partners, will work to achieve cost-effective reductions of key emissions hotspots across the offshore wind value chain.
Speaker #2: Reducing value chain emissions is essential from a climate impact perspective and will improve our value proposition in future offshore wind auctions. Turning to the operational highlights of the first half of the year.
Speaker #2: I'm very satisfied with our operational performance. Our EBITDA, excluding new partnerships and cancellation fees, amounts to DKK 15 billion, which is an increase of more than DKK 1 billion compared to the first half of 2025.
Speaker #2: This was driven by ramp-up generation in offshore and slightly higher than normal wind speeds. The performance was also supported by good availability within our offshore business.
Rasmus Errboe: This was driven by ramp-up generation in offshore and slightly higher than normal wind speeds. The performance was also supported by good availability within our offshore business. Our financials for the H1 of the year keeps us fully on track to deliver on our full year guidance. When it comes to safety, we have seen an increase in our total recordable injury rate compared to H1 2025. The increase was primarily driven by an incident related to food poisoning at one of our power plants, which we consider a one-off event. In addition, the organizational adjustments undertaken means that a reduced share of our colleagues are working in the offices and relatively more are working directly at our assets.
Rasmus Errboe: This was driven by ramp-up generation in offshore and slightly higher than normal wind speeds. The performance was also supported by good availability within our offshore business. Our financials for the H1 of the year keeps us fully on track to deliver on our full year guidance. When it comes to safety, we have seen an increase in our total recordable injury rate compared to H1 2025. The increase was primarily driven by an incident related to food poisoning at one of our power plants, which we consider a one-off event. In addition, the organizational adjustments undertaken means that a reduced share of our colleagues are working in the offices and relatively more are working directly at our assets.
Speaker #2: Our finances for the first half of the year keeps us fully on track to deliver on our full-year guidance. When it comes to safety, we have seen an increase in our total recordable injury rate, compared to first half of 2025.
Speaker #2: The increase was primarily driven by an incident related to food poisoning at one of our power plants, which we consider a one-off event. In addition, the organization adjustments undertaken means that a reduced share of our colleagues are working in the offices and relatively more are working directly at our assets.
Speaker #2: Safety remains a top priority for us and our employees, and we continue to strengthen our safety commitments through targeted initiatives and sharing of best practices with suppliers, all aimed at preventing incidents and bringing our people home safe every day.
Rasmus Errboe: Safety remains a top priority for us and our employees, and we continue to strengthen our safety commitments through targeted initiatives and sharing of best practices with suppliers, all aimed at preventing incidents and bringing our people home safe every day. Let's turn to slide 6 and an overview of our construction portfolio. I will start by covering our projects that are near commissioning and subsequently cover the other projects individually in more detail. For Borkum Riffgrund 3, turbine commissioning is progressing as planned. The project is more than 99% complete, and we are expecting to commission the project during the Q3. For Greater Changhua 2B and 4, the project ensured further progress during the quarter as all turbines at Greater Changhua 4 have started producing power and completed all main scopes.
Rasmus Errboe: Safety remains a top priority for us and our employees, and we continue to strengthen our safety commitments through targeted initiatives and sharing of best practices with suppliers, all aimed at preventing incidents and bringing our people home safe every day. Let's turn to slide 6 and an overview of our construction portfolio. I will start by covering our projects that are near commissioning and subsequently cover the other projects individually in more detail. For Borkum Riffgrund 3, turbine commissioning is progressing as planned. The project is more than 99% complete, and we are expecting to commission the project during the Q3. For Greater Changhua 2B and 4, the project ensured further progress during the quarter as all turbines at Greater Changhua 4 have started producing power and completed all main scopes.
Speaker #2: Let's turn to slide 6, and an overview of our construction portfolio. I will start by covering our projects that are near commissioning and subsequently cover the other projects individually in more detail.
Speaker #2: For Borgum Rifgrunn 3, turbine commissioning is progressing as planned. The project is more than 99% complete, and we are expecting to commission the project during the third quarter.
Speaker #2: For Greater Chiang Mai 2B and 4, the project ensured further progress during the quarter as all turbines at Greater Chiang Mai 4 have started producing power and completed all main scopes.
Speaker #2: In addition, the project has completed all the onshore works related to the upcoming repair of the export cable related to Greater Chiang Mai 2B.
Rasmus Errboe: In addition, the project has completed all the onshore works related to the upcoming repair of the export cable related to Greater Changhua 2B. With this, the degree of completion is now at 85%, up from 80% in the Q1. The project remains focused on the installation and initialization of the export cable for the Greater Changhua 2B section. The repair work is expected to be completed in the coming period, and subsequently the export cable will be energized before turbines commissionings will commence. The project remains on schedule for commissioning at the back end of the Q3. For Revolution Wind in the US, the project continues to ramp up production with the commissioning of turbines. Currently, the project has 61 of the 65 turbines installed, and the project intends to install the remaining turbines this year.
Rasmus Errboe: In addition, the project has completed all the onshore works related to the upcoming repair of the export cable related to Greater Changhua 2B. With this, the degree of completion is now at 85%, up from 80% in the Q1. The project remains focused on the installation and initialization of the export cable for the Greater Changhua 2B section. The repair work is expected to be completed in the coming period, and subsequently the export cable will be energized before turbines commissionings will commence. The project remains on schedule for commissioning at the back end of the Q3. For Revolution Wind in the US, the project continues to ramp up production with the commissioning of turbines. Currently, the project has 61 of the 65 turbines installed, and the project intends to install the remaining turbines this year.
Speaker #2: With this, the degree of completion is now at 85% up from 80% in the first quarter. The project remains focused on the installation and energization of the export cable for the Greater Chiang Mai 2B section.
Speaker #2: The repair work is expected to be completed in the coming period, and, subsequently, the export cable will be energized before turbine commissioning commences.
Speaker #2: The project remains on schedule for commissioning at the back end of the third quarter. For Revolution Wind in the US, the project continues to ramp up production with the commissioning of turbines.
Speaker #2: Currently, the project has 61 of the 65 turbines installed. And the project intends to install the remaining turbines this year. The project is more than 95% complete, and the project remains on track towards full commercial operations in the second half of 2026.
Rasmus Errboe: The project is more than 95% complete, and the project remains on track towards full commercial operations in H2 2026. Turning to slide seven and an update on our Baltica 2 project in Poland. During the quarter, the project has made significant progress, particularly with the installation of monopile foundations. Since the installation campaign was initiated in May this year, the project has installed 103 monopile foundations out of the planned 111, including all four of the monopile foundations for the offshore substations. This is a significant achievement by the team and a testament to the execution ability. With the progress achieved during the quarter, the degree of completion has increased to approximately 40%, up from 30% in Q1.
Rasmus Errboe: The project is more than 95% complete, and the project remains on track towards full commercial operations in H2 2026. Turning to slide seven and an update on our Baltica 2 project in Poland. During the quarter, the project has made significant progress, particularly with the installation of monopile foundations. Since the installation campaign was initiated in May this year, the project has installed 103 monopile foundations out of the planned 111, including all four of the monopile foundations for the offshore substations. This is a significant achievement by the team and a testament to the execution ability. With the progress achieved during the quarter, the degree of completion has increased to approximately 40%, up from 30% in Q1.
Speaker #2: Turning to slide 7, and an update on our Baltica 2 project in Poland. During the quarter, the project has made significant progress, particularly with the installation of monopile foundations.
Speaker #2: Since the installation campaign was initiated in May this year, the project has installed 103 monopile foundations out of the planned 111, including all four of the monopile foundations for the offshore substations.
Speaker #2: This is a significant achievement by the team, and a testament to the execution ability. With the progress achieved during the quarter, the degree of completion has increased to approximately 40% up from 30% in the first quarter.
Speaker #2: For the offshore substations, the manufacturing of the structures is progressing as planned, and in the third quarter, all four topsides will be transported to the site for installation later this year.
Rasmus Errboe: For the offshore substations, the manufacturing of the structures is progressing as planned, and in Q3, all four top sides will be transported to the site for installation later this year. The fabrication of the export and array cables are progressing as planned, with two of the four export cables having passed final acceptance tests. The onshore substation work is well progressed and nearing completion, with onshore cables manufactured and installation on schedule. In the coming period, the focus of the project will be the continued installation of the remaining turbine foundations and secondary structures, as well as tracking progress on the cable manufacturing. The load-out and transportation of the two complete export cables will commence in Q3. The work on the onshore substation will continue, including termination of the cables to the onshore substation.
Rasmus Errboe: For the offshore substations, the manufacturing of the structures is progressing as planned, and in Q3, all four top sides will be transported to the site for installation later this year. The fabrication of the export and array cables are progressing as planned, with two of the four export cables having passed final acceptance tests. The onshore substation work is well progressed and nearing completion, with onshore cables manufactured and installation on schedule. In the coming period, the focus of the project will be the continued installation of the remaining turbine foundations and secondary structures, as well as tracking progress on the cable manufacturing. The load-out and transportation of the two complete export cables will commence in Q3. The work on the onshore substation will continue, including termination of the cables to the onshore substation.
Speaker #2: The fabrication of the export and array cables are progressing as planned, with two of the four export cables having passed final acceptance tests. The onshore substation work is well progressed, and nearing completion.
Speaker #2: With onshore cables manufactured and installation on schedule, the focus of the project in the coming period will be the continued installation of the remaining turbine foundations and secondary structures, as well as tracking progress on the cable manufacturing.
Speaker #2: Also, the loadout and transportation of the two complete export cables will commence in the third quarter. Finally, the work on the onshore substation will continue, including termination of the cables to the onshore substation.
Speaker #2: Turning to slide 8, an update on our Sunrise Wind project in the US. During the quarter, the project has continued to make solid progress.
Rasmus Errboe: Turning to slide eight and an update on our Sunrise Wind project in the US. During the quarter, the project has continued to make solid progress. This includes both progress on the installation of turbine foundations, array cables, and turbines. With the progress achieved during the quarter, the degree of completion has increased to approximately 50%, up from 47% in Q1. For the installation of turbine foundations, the work has been resumed after the seasonal installation restrictions ended in May. Since the installation resumed, it has progressed well, with 77 of the 84 positions now installed. The remaining work on foundation installation is planned to be completed within the current installation window. On turbine installation, a total of 20 turbines and 20 array cables have been installed. On the export cable, all sections have been installed, joined, and energized, and the offshore converter station has been energized.
Rasmus Errboe: Turning to slide eight and an update on our Sunrise Wind project in the US. During the quarter, the project has continued to make solid progress. This includes both progress on the installation of turbine foundations, array cables, and turbines. With the progress achieved during the quarter, the degree of completion has increased to approximately 50%, up from 47% in Q1. For the installation of turbine foundations, the work has been resumed after the seasonal installation restrictions ended in May. Since the installation resumed, it has progressed well, with 77 of the 84 positions now installed. The remaining work on foundation installation is planned to be completed within the current installation window. On turbine installation, a total of 20 turbines and 20 array cables have been installed. On the export cable, all sections have been installed, joined, and energized, and the offshore converter station has been energized.
Speaker #2: This includes both progress on the installation of turbine foundations, array cables, and turbines. With the progress achieved during the quarter, the degree of completion has increased to approximately 50% up from 47% in the first quarter.
Speaker #2: For the installation of turbine foundations, the work has been resumed after the seasonal installation restrictions ended in May. Since the installation resumed, it has progressed well.
Speaker #2: With 77 of the 84 positions now installed. The remaining work on foundation installation is planned to be completed within the current installation window. On turbine installation a total of 20 turbines and 20 array cables have been installed.
Speaker #2: On the export cable, all sections have been installed, joined, and energized, and the offshore converter station has been energized. For the onshore substation, the converter station and export cable route is complete.
Rasmus Errboe: For the onshore substation, the converter station and export cable route is complete. In terms of turbine fabrication, all equipment remaining to be installed have been manufactured. In the coming period, the project is expected to complete monopile installation and continue the installation of turbines and array cables. Commissioning works will also continue in the offshore converter station, and the project is expected to start commissioning of turbines later this year. Turning to slide nine and an update on the progress at Hornsea 3 in the UK. The project has made further progress across several scopes. Since the commencement of turbine foundation installation, the project has installed 43 out of the total of 197 positions. With the progress achieved during the quarter, the degree of completion has increased to approximately 30%, up from 25% in Q1.
Rasmus Errboe: For the onshore substation, the converter station and export cable route is complete. In terms of turbine fabrication, all equipment remaining to be installed have been manufactured. In the coming period, the project is expected to complete monopile installation and continue the installation of turbines and array cables. Commissioning works will also continue in the offshore converter station, and the project is expected to start commissioning of turbines later this year. Turning to slide nine and an update on the progress at Hornsea 3 in the UK. The project has made further progress across several scopes. Since the commencement of turbine foundation installation, the project has installed 43 out of the total of 197 positions. With the progress achieved during the quarter, the degree of completion has increased to approximately 30%, up from 25% in Q1.
Speaker #2: In terms of turbine fabrication, all equipment remaining to be installed have been manufactured. In the coming period, the project is expected to complete monopile installation and continue the installation of turbines and array cables.
Speaker #2: Commissioning works will also continue in the offshore converter station, and the project is expected to start commissioning of turbines later this year. Turning to slide 9, and an update on the progress at Hornsea 3 in the UK.
Speaker #2: The project has made further progress across several scopes. Since the commencement of turbine foundation installation, the project has installed 43 out of the total of 197 positions.
Speaker #2: With the progress achieved during the quarter, the degree of completion has increased to approximately 30%, up from 25% in the first quarter. Regarding the enabling and reinforcement works at the Norwich Main substation, where the project is due to connect to the UK transmission grid, the work is progressing according to the updated schedule and is expected to be completed next month.
Rasmus Errboe: Regarding the enabling and reinforcement works at the Norwich Main Substation, where the project is due to connect to the UK transmission grid, the work is progressing according to the updated schedule and expected to be completed next month. We are continuing to engage closely with National Grid Electricity Transmission and the National Energy System Operator as they work to minimize the delay and mitigate any further delays from occurring and impacting the schedule. On the export cable, the installation work has continued. For the offshore converter station that is already installed, the associated export cable has also now been installed and tested, and is ready for energization. For the export cable to be installed at the project's second offshore converter station, the nearshore section has also been installed. Manufacturing of the mid and far shore section is complete and is planned to start installation later in the year.
Rasmus Errboe: Regarding the enabling and reinforcement works at the Norwich Main Substation, where the project is due to connect to the UK transmission grid, the work is progressing according to the updated schedule and expected to be completed next month. We are continuing to engage closely with National Grid Electricity Transmission and the National Energy System Operator as they work to minimize the delay and mitigate any further delays from occurring and impacting the schedule. On the export cable, the installation work has continued. For the offshore converter station that is already installed, the associated export cable has also now been installed and tested, and is ready for energization. For the export cable to be installed at the project's second offshore converter station, the nearshore section has also been installed. Manufacturing of the mid and far shore section is complete and is planned to start installation later in the year.
Speaker #2: We are continuing to engage closely with national grid electricity transmission and the national energy system operator, as they work to minimize the delay and mitigate any further delays from occurring and impacting the schedule.
Speaker #2: On the export cable, the installation work has continued. For the offshore converter station that is already installed, the associated export cable has also now been installed, and tested, and is ready for energization.
Speaker #2: For the export cable to be installed at the project's second offshore converter station, the nearshore section has also been installed. The manufacturing of the mid and farshore section is complete, and is planned to start installation later in the year.
Speaker #2: In the coming period, the focus of the project is to progress foundation installation according to plan. With the manufacturing and supply of foundations on track.
Rasmus Errboe: In the coming period, the focus of the project is to progress foundation installation according to plan. With the manufacturing and supply of foundations on track, the installation of the project's second offshore converter station is planned for Q3. Finally, the installation of the turbines is planned to start later this year, with two installation vessels that are currently active on other projects before commencing work on Hornsea 3. With this, let me hand over the word to you, Trond.
Rasmus Errboe: In the coming period, the focus of the project is to progress foundation installation according to plan. With the manufacturing and supply of foundations on track, the installation of the project's second offshore converter station is planned for Q3. Finally, the installation of the turbines is planned to start later this year, with two installation vessels that are currently active on other projects before commencing work on Hornsea 3. With this, let me hand over the word to you, Trond.
Speaker #2: Also, the installation of the project's second offshore converter station is planned for the third quarter. And finally, the installation of the turbines is planned to start later this year, with two installation vessels that are currently active on other projects before commencing work on Hornsea 3.
Speaker #2: With this, let me hand over the word to you, Todd.
Speaker #1: Thank you, Rasmus. And good afternoon, everyone. Let's start with slide 11 and the EPDA for the second quarter of '26. As always, unless I state otherwise, the numbers I refer to will be in Danish kroner.
Trond Westlie: Thank you, Rasmus, and good afternoon, everyone. Let's start with slide 11 and the EBITDA for Q2 2026. As always, unless I state otherwise, the numbers I refer to will be in DKK. In the quarter, our operational performance was in line with expectations, and we delivered an EBITDA excluding new partnerships and cancellation fees of DKK 5.4 billion. Let me walk you through the main developments. For our offshore business, total earnings came in DKK 400 million higher than last year, coming from higher earnings within construction agreements, partly offset by slightly lower sites earnings. Sites earnings came in DKK 200 million lower compared to last year. In this Q2, our trading business delivered earnings as expected, but not to the same extent as last year. During the quarter, a planned maintenance outage at Hornsea 1 during most of June also impacted earnings.
Trond Westlie: Thank you, Rasmus, and good afternoon, everyone. Let's start with slide 11 and the EBITDA for Q2 2026. As always, unless I state otherwise, the numbers I refer to will be in DKK. In the quarter, our operational performance was in line with expectations, and we delivered an EBITDA excluding new partnerships and cancellation fees of DKK 5.4 billion. Let me walk you through the main developments. For our offshore business, total earnings came in DKK 400 million higher than last year, coming from higher earnings within construction agreements, partly offset by slightly lower sites earnings. Sites earnings came in DKK 200 million lower compared to last year. In this Q2, our trading business delivered earnings as expected, but not to the same extent as last year. During the quarter, a planned maintenance outage at Hornsea 1 during most of June also impacted earnings.
Speaker #1: In the quarter our operational performance was in line with expectations, and we delivered an EPDA excluding new partnerships and cancellation fees of 5.4 billion.
Speaker #1: Let me walk you through the main developments. For our offshore business, total earnings came in 400 million higher than last year, coming from higher earnings within construction agreements, partly offset by slightly lower sites' earnings.
Speaker #1: Sites' earnings came in 200 million lower compared to last year. In this second quarter, our trading business delivered earnings as expected, but not to the same extent as last year.
Speaker #1: During the quarter, a planned maintenance outage at Hornsea 1, during most of June, also impacted earnings. And finally, there was a year-over-year effect from good wind 1 and good wind 2, gradually stepping out of its subsidy during the first half year, and is further reflected in our failure guidance.
Trond Westlie: Finally, there was a year-over-year effect from Gode Wind 1 and Gode Wind 2 gradually stepping out of its subsidy during H1 and is fully reflected in our full-year guidance. This was partly offset by higher wind speeds in the quarter as well as higher power prices. Earnings from offshore sites, excluded contribution from trading activities, was approximately 5% higher than the same period last year. Earnings within existing partnership increased compared to last year, mainly related to construction agreement from Hornsea 3 and updates to other construction agreements. In our onshore business, earnings decreased by approximately DKK 200 million to last year. This was mainly due to sale of components in Q2 of last year, which was not repeated this quarter, while earnings from offshore sites were at the same level as last year.
Trond Westlie: Finally, there was a year-over-year effect from Gode Wind 1 and Gode Wind 2 gradually stepping out of its subsidy during H1 and is fully reflected in our full-year guidance. This was partly offset by higher wind speeds in the quarter as well as higher power prices. Earnings from offshore sites, excluded contribution from trading activities, was approximately 5% higher than the same period last year. Earnings within existing partnership increased compared to last year, mainly related to construction agreement from Hornsea 3 and updates to other construction agreements. In our onshore business, earnings decreased by approximately DKK 200 million to last year. This was mainly due to sale of components in Q2 of last year, which was not repeated this quarter, while earnings from offshore sites were at the same level as last year.
Speaker #1: This was partly offset by higher wind speeds in the quarter, as well as higher power prices. Earnings from offshore sites excluded contribution from trading activities, was approximately 5% higher than the same period last year.
Speaker #1: Earnings went in existing partnership increased compared to last year, mainly related to construction agreement from Hornsea 3, and updates to other construction agreements. In our onshore business, earnings decreased by approximately 200 million to last year.
Speaker #1: This was mainly due to the sale of components in the second quarter of last year, which was not repeated this quarter, while earnings from offshore sites were at the same level as last year.
Speaker #1: Within bioenergy and other, earnings were in line with last year, driven by higher generation and prices at our combined heat and power plants. This was offset by lower contribution from ancillary services, and a provision related to our gas storage system.
Trond Westlie: Within bioenergy and other, earnings were in line with last year, driven by higher generation and prices at our combined heat and power plants. This was offset by lower contribution from ancillary services and a provision related to our gas storages. Going to slide 12, in Q2 2026, we incurred a non-cash impairment loss of DKK 1.2 billion relating to our US offshore project as a result of an increase in the long-dated US interest rates. Our net profit for the quarter totaled DKK 700 million. Compared to last year, net profit was impacted by non-cash impairment loss that I have just described, as well as lower EBITDA from new partnerships in Q2 2025 that were not repeated in this quarter. Net profit adjusted for impairments, new partnerships, and cancellation fees amounted to DKK 1.9 billion this quarter versus DKK 2.1 billion in the same quarter last year.
Trond Westlie: Within bioenergy and other, earnings were in line with last year, driven by higher generation and prices at our combined heat and power plants. This was offset by lower contribution from ancillary services and a provision related to our gas storages. Going to slide 12, in Q2 2026, we incurred a non-cash impairment loss of DKK 1.2 billion relating to our US offshore project as a result of an increase in the long-dated US interest rates. Our net profit for the quarter totaled DKK 700 million. Compared to last year, net profit was impacted by non-cash impairment loss that I have just described, as well as lower EBITDA from new partnerships in Q2 2025 that were not repeated in this quarter. Net profit adjusted for impairments, new partnerships, and cancellation fees amounted to DKK 1.9 billion this quarter versus DKK 2.1 billion in the same quarter last year.
Speaker #1: Then going to slide 12. In the second quarter of '26, we incurred a non-cash impairment loss of 1.2 billion, relating to our US offshore project, as a result of an increase in the long-dated US interest rates.
Speaker #1: Our net profit for the quarter totaled 700 million, compared to last year, net profit was impacted by non-cash impairment loss that I just described, as well as lower EPDA from new partnerships, in second quarter of '25 that were not repeated in this quarter.
Speaker #1: Net profit adjusted for impairments, new partnerships and cancellation fees, amounted to 1.9 billion this quarter, versus 2.1 billion in the same quarter last year.
Speaker #1: Adjusted for impairment and cancellation fees, our return on capital employed came in at 6.6%, a decrease compared to last year due to lower EPDA for the 12 months period, and higher capital employed.
Trond Westlie: Adjusted for impairment and cancellation fees, our return on capital employed came in at 6.6%, a decrease compared to last year due to lower EBITDA for the 12 months period and higher capital employed. The reported return on capital employed came in at 3.1%. Let us turn to slide 13 and our net interest-bearing debt and credit metrics. At the end of Q2, our net debt amounted to DKK 22 billion, representing an increase of DKK 700 million during the quarter. Cash flow operating activities included contribution from our operational earnings, as well as work in progress relating to the offshore construction portfolio and changes in other working capital. Divestments mainly relate to the sale of our European onshore portfolio. Our gross investments amounted to DKK 10.1 billion, reflecting the continued investment into our renewable construction projects.
Trond Westlie: Adjusted for impairment and cancellation fees, our return on capital employed came in at 6.6%, a decrease compared to last year due to lower EBITDA for the 12 months period and higher capital employed. The reported return on capital employed came in at 3.1%. Let us turn to slide 13 and our net interest-bearing debt and credit metrics. At the end of Q2, our net debt amounted to DKK 22 billion, representing an increase of DKK 700 million during the quarter. Cash flow operating activities included contribution from our operational earnings, as well as work in progress relating to the offshore construction portfolio and changes in other working capital. Divestments mainly relate to the sale of our European onshore portfolio. Our gross investments amounted to DKK 10.1 billion, reflecting the continued investment into our renewable construction projects.
Speaker #1: The reported return on capital employed came in at 3.1%. Let's turn to slide 13, and our net interest bearing debt and credit metrics. At the end of second quarter, a net debt amounted to 22 billion, representing an increase of 700 million during the quarter.
Speaker #1: Cash flow from operating activities included contributions from our operational earnings, as well as work in progress relating to the offshore construction portfolio and changes in other working capital.
Speaker #1: Divestments, mainly relate to the sale of our European onshore portfolio. Our gross investments amounted to 10.1 billion, reflecting the continued investment into our renewable construction projects.
Speaker #1: Our credit metric, FFO2 adjusted net debt, stood approximately at 45% at the end of the second quarter, which is well in line with our target of more than 30%.
Trond Westlie: Our credit metric, FFO to adjusted net debt, stood approximately at 45% at the end of Q2, which is well in line with our target of more than 30%. The increase is driven by an increase in the fund from operation over the last 12 months, the proceeds from the rights issue, and closing of various farm downs. At the end of the quarter, we had a total liquidity reserve of more than DKK 115 billion. We remain committed to a solid investment-grade rating, and in early July, we discontinued the rating agent with Standard & Poor's as we continuously review the cost benefit of maintaining multiple ratings and concluded that Moody's and Fitch provide sufficient coverage for our investor base. The decision will not change our funding plan or how we will be utilizing hybrids as they remain a permanent part of our capital stack.
Trond Westlie: Our credit metric, FFO to adjusted net debt, stood approximately at 45% at the end of Q2, which is well in line with our target of more than 30%. The increase is driven by an increase in the fund from operation over the last 12 months, the proceeds from the rights issue, and closing of various farm downs. At the end of the quarter, we had a total liquidity reserve of more than DKK 115 billion. We remain committed to a solid investment-grade rating, and in early July, we discontinued the rating agent with Standard & Poor's as we continuously review the cost benefit of maintaining multiple ratings and concluded that Moody's and Fitch provide sufficient coverage for our investor base. The decision will not change our funding plan or how we will be utilizing hybrids as they remain a permanent part of our capital stack.
Speaker #1: The increase is driven by an increase in the funds from operations over the last 12 months, the proceeds from the rights issue, and the closing of various farm-downs.
Speaker #1: At the end of the quarter, we had a total liquidity reserve of more than 115 billion. We remain committed to a solid investment-grade rating, and in early July, we discontinued the rating agent with the standard enforced, as we continuously review the cross the cost-benefit of maintaining multiple ratings, and concluded that Moody's and Fitch provide sufficient coverage for our investment investor base.
Speaker #1: The decision will not change our funding plan or how we will be utilizing hybrids, as they remain a permanent part of our capital stack.
Speaker #1: However, the decision will reduce the administrative burden and fees without affecting our capital market access. Turning to slide 14, I will introduce the dividend policy within our capital allocation principles.
Trond Westlie: However, the decision will reduce the administrative burden and fees without affecting our capital market access. Turning to slide 14, I will introduce the dividend policy within our capital allocation principles. Our capital allocation principles remain unchanged and are in a ranked order. Firstly, to have a strong balance sheet targeting an FFO to adjusted net debt above 30%, which is aligned with a solid investment-grade rating, as I just mentioned. Secondly, to reinstate the dividend for the financial year 2026, as we have committed. Thirdly, a disciplined approach to pursue value creating opportunities for further growth. Finally, we will consider additional shareholder remuneration should we be over-capitalized after 2027. As previously communicated, we target to reinstate the dividend as part of the financial year 2026, with the first payout in 2027.
Trond Westlie: However, the decision will reduce the administrative burden and fees without affecting our capital market access. Turning to slide 14, I will introduce the dividend policy within our capital allocation principles. Our capital allocation principles remain unchanged and are in a ranked order. Firstly, to have a strong balance sheet targeting an FFO to adjusted net debt above 30%, which is aligned with a solid investment-grade rating, as I just mentioned. Secondly, to reinstate the dividend for the financial year 2026, as we have committed. Thirdly, a disciplined approach to pursue value creating opportunities for further growth. Finally, we will consider additional shareholder remuneration should we be over-capitalized after 2027. As previously communicated, we target to reinstate the dividend as part of the financial year 2026, with the first payout in 2027.
Speaker #1: Our capital allocation principles remain unchanged on our in a ranked order firstly, to have a strong balance sheet, targeting an FFF to adjusted net debt above 30%, which is aligned with a solid investment-grade rating, as I just mentioned.
Speaker #1: Secondly, to reinstate the dividend for the financially year 2026, as we have committed to. And thirdly, a disciplined approach to pursue value creating opportunities for further growth.
Speaker #1: Finally, we will consider additional shareholder remuneration should we be overcapitalized after 2027. As previously communicated, we target to reinstate the dividend as part of the financially year 2026, with the first payout in 2027.
Speaker #1: This dividend policy will replace the previous one, and the policy will apply for the financial years '26 to '28. The dividend amount will be announced together with the annual report for 2026 in February, of '27, and formally proposed by the board of directors when calling for the annual general meeting in 2027.
Trond Westlie: This dividend policy will replace the previous one, and the policy will apply for the financial years 2026 to 2028. The dividend amount will be announced together with the annual report for 2026 in February of 2027, and formally proposed by the board of directors when calling for the annual general meeting in 2027. We believe that within total shareholder returns, we can create more value through earnings growth rather than through higher dividend yield, as the fundamentals and outlook for offshore wind across our core markets are strong. As such, the initial dividend level will be set reflecting, one, our continued commitment to a strong capital structure aligned with a solid investment grade rating. Two, the ongoing investments into 8.1 gigawatts offshore wind construction program through 2027. That includes, of course, the DKK 90 billion of capital committed through 2026 and 2027.
Trond Westlie: This dividend policy will replace the previous one, and the policy will apply for the financial years 2026 to 2028. The dividend amount will be announced together with the annual report for 2026 in February of 2027, and formally proposed by the board of directors when calling for the annual general meeting in 2027. We believe that within total shareholder returns, we can create more value through earnings growth rather than through higher dividend yield, as the fundamentals and outlook for offshore wind across our core markets are strong. As such, the initial dividend level will be set reflecting, one, our continued commitment to a strong capital structure aligned with a solid investment grade rating. Two, the ongoing investments into 8.1 gigawatts offshore wind construction program through 2027. That includes, of course, the DKK 90 billion of capital committed through 2026 and 2027.
Speaker #1: We believe that within total shareholder returns, we can create more value through earnings growth rather than through higher dividend yield, as the fundamentals and outlook for offshore wind across our core markets are strong.
Speaker #1: As such, the initial dividend level will be set reflecting one, our continued commitment to a strong capital structure aligned with the solid investment-grade rating, two, the ongoing investments into 8.1 gigawatts offshore wind construction program through '27, that includes of course the 90 billion of capital committed through 2026 and 2027.
Trond Westlie: Three, the uncertainties regarding the ongoing regulatory risk for offshore wind in the US, together with ongoing legal and arbitration proceedings. Four, our opportunities to invest into new value creating growth. Within this policy, the dividend amount is expected to start at a modest level and increase each year. As part of our Q2 2026 consensus, we received 13 contribution on dividend per share for 2026, ranging from two kronors a share to five kronors a share. While no decision have been made at this point in time, we currently expect that the starting point of our dividend distribution to be in the lower part of this range. Finally, let's turn to slide 15 on our outlook for 2026.
Trond Westlie: Three, the uncertainties regarding the ongoing regulatory risk for offshore wind in the US, together with ongoing legal and arbitration proceedings. Four, our opportunities to invest into new value creating growth. Within this policy, the dividend amount is expected to start at a modest level and increase each year. As part of our Q2 2026 consensus, we received 13 contribution on dividend per share for 2026, ranging from two kronors a share to five kronors a share. While no decision have been made at this point in time, we currently expect that the starting point of our dividend distribution to be in the lower part of this range. Finally, let's turn to slide 15 on our outlook for 2026.
Speaker #1: Three, the uncertainties regarding the ongoing regulatory risk for offshore wind in the US, together with ongoing legal and arbitration proceedings. And four, our opportunities to invest into new value creating growth.
Speaker #1: Within this policy, the dividend amount is expected to start at a modest level and increase each year. As part of our second quarter 2026 consensus, we received 13 contributions on dividend per share for '26, ranging from 2 kroner a share to 5 kroner a share.
Speaker #1: And while no decisions have been made at this point in time, we currently expect that the starting point of our dividend distribution will be in the lower part of this range.
Speaker #1: Finally, let's turn to slide 15, and our outlook for '26. With the operational performance and progress in on our construction portfolio, in line with expectation for the second quarter, we maintain our full year EBITDA guidance, excluding new partnerships and cancellation fees of more than 28 billion.
Trond Westlie: With the operational performance and progress on our construction portfolio, in line with expectation for the Q2, we maintain our full year EBITDA guidance, excluding new partnerships and cancellation fees of more than DKK 28 million. We still expect the offshore business to come in higher than last year and onshore in line with 2025. We have changed the directional guidance for bioenergy and other from in line to lower due to the lower contribution from ancillary services, and a provision related to our gas storages in Q2 in 2026. On CapEx, we maintain our gross investment guidance for 2026 of DKK 50 to 55 billion. With that, we will now open for questions. Operator, please.
Trond Westlie: With the operational performance and progress on our construction portfolio, in line with expectation for the Q2, we maintain our full year EBITDA guidance, excluding new partnerships and cancellation fees of more than DKK 28 million. We still expect the offshore business to come in higher than last year and onshore in line with 2025. We have changed the directional guidance for bioenergy and other from in line to lower due to the lower contribution from ancillary services, and a provision related to our gas storages in Q2 in 2026. On CapEx, we maintain our gross investment guidance for 2026 of DKK 50 to 55 billion. With that, we will now open for questions. Operator, please.
Speaker #1: We still expect the offshore wind offshore business to come in higher than last year, and onshore in line with '25. We have changed the directional guidance for bioenergy and other from in line to lower due to the lower contribution from ancillary services and a provision related to our gas storages in second quarter in '26.
Speaker #1: On capex, we maintain our gross investment guidance for 2026 of $50 to $55 billion. And with that, we will now open for questions. Operator, please.
Speaker #2: We will now begin the question and answer session. Anyone who wishes to ask a question may press star and one on the telephone. You will hear a tone to confirm that you have entered the queue.
Operator: We will now begin the question and answer session. Anyone who wishes to ask a question may press star and one on the telephone. You will hear a tone to confirm that you have entered the queue. If you wish to remove yourself from the question queue, you may press star and two. Questioners on the phone are requested to disable the loudspeaker mode while asking a question. Please respect only one question per participant, and then you can go back to the queue for a second question. Anyone who has a question may press star and one at this time. The first question comes from the line of Casper Blom from Danske Bank. Please go ahead.
Operator: We will now begin the question and answer session. Anyone who wishes to ask a question may press star and one on the telephone. You will hear a tone to confirm that you have entered the queue. If you wish to remove yourself from the question queue, you may press star and two. Questioners on the phone are requested to disable the loudspeaker mode while asking a question. Please respect only one question per participant, and then you can go back to the queue for a second question. Anyone who has a question may press star and one at this time. The first question comes from the line of Casper Blom from Danske Bank. Please go ahead.
Speaker #2: If you wish to remove yourself from the question queue, you may press star and two. Questioners on the phone are requested to disable the loudspeaker mode while asking a question.
Speaker #2: And please respect only one question per participant, and then you can go back to the queue for a second question. Anyone who has a question may press star and one at this time.
Speaker #2: The first question comes from the line of Caspar Blom from Danske Bank. Please go ahead.
Speaker #3: Thank you very much. And the first question from my side goes to the slide Trond has almost just presented about capital allocation. And the point about potential rebalancing measures if overcapitalized post 2027.
Casper Blom: Thank you very much. The first question from my side goes to the slide Trond has almost just presented about capital allocation and the point about potential rebalancing measures if overcapitalized post 2027. I assume this is a point that you have put in order to address the potential situation that you will run out of projects to construct when done with the current construction portfolio. I was wondering if you could give any kind of indication as to when you would regard the balance sheet as being overcapitalized. Is there a certain level of debt to EBITDA or FFO, whatever measure you would be looking at, where you would say, "Okay, now we need to start returning cash somehow to shareholders." Thank you.
Casper Blom: Thank you very much. The first question from my side goes to the slide Trond has almost just presented about capital allocation and the point about potential rebalancing measures if overcapitalized post 2027. I assume this is a point that you have put in order to address the potential situation that you will run out of projects to construct when done with the current construction portfolio. I was wondering if you could give any kind of indication as to when you would regard the balance sheet as being overcapitalized. Is there a certain level of debt to EBITDA or FFO, whatever measure you would be looking at, where you would say, "Okay, now we need to start returning cash somehow to shareholders." Thank you.
Speaker #3: I assume this is a point that you've put in in order to address the potential situation that your runout of projects to construct when done with the current construction portfolio.
Speaker #3: I was wondering if you could give any kind of indication as to when you would regard the balance sheet as being overcapitalized, is there a certain level of debt to EBITDA or FFO, whatever measure you would be looking at, where you would say, okay, now we need to start returning cash somehow to shareholders.
Speaker #3: Thank you.
Speaker #1: Hi, Casper. Thank you, thank you very much. As Trond also alluded to, we obviously have an implicit prioritization in our capital allocation principles.
Rasmus Errboe: Hi, Casper. Thank you. Thank you very much. As Trond also alluded to, we obviously have an implicit prioritization in our capital allocation principles, where rebalancing is number 4 of the 4. I am quite bullish about our potential for laying the foundation for profitable growth for our shareholders. We see ourselves as a growth company. We have set a new strategic direction last year. During the first 18 months of our turnaround plan, we have, which is also evident from this quarter, continued to deliver according to plan across all of the four priorities that we have as part of the updated strategy. There is nothing that I have seen in. Let me put it differently.
Rasmus Errboe: Hi, Casper. Thank you. Thank you very much. As Trond also alluded to, we obviously have an implicit prioritization in our capital allocation principles, where rebalancing is number 4 of the 4. I am quite bullish about our potential for laying the foundation for profitable growth for our shareholders. We see ourselves as a growth company. We have set a new strategic direction last year. During the first 18 months of our turnaround plan, we have, which is also evident from this quarter, continued to deliver according to plan across all of the four priorities that we have as part of the updated strategy. There is nothing that I have seen in. Let me put it differently.
Speaker #1: Where rebalancing is a number four of the four. We are IAM quite bullish about our potential for laying the foundation for profitable growth for our shareholders.
Speaker #1: We see ourselves as a growth company. We have set a new strategic direction last year. During the first 18 months of our turnaround planned, we have which is also evident from this quarter, continued to deliver according to plan across all of the four priorities that we have as part of the updated strategy.
Speaker #1: There is nothing that I have seen—or let me put it differently—everything that I have seen, especially in Europe on the offshore wind side during the last 18 months, has only made me more confident in the attractiveness of the market going forward, while obviously continuing to have a razor-sharp focus on value and very disciplined bidding on our side.
Rasmus Errboe: Everything that I have seen, especially in Europe on the offshore wind side during the last 18 months, have only made me more confident in the attractiveness of the market going forward, while obviously continuing to have a razor-sharp focus on value and a very disciplined bidding on our side. If I look at the opportunities in all of our core markets, there are five, as an example, tenders coming up during the next 12 months, all with frameworks that make sense to us. Broadly speaking, there is ample opportunity for us to achieve sufficiently profitable growth for our shareholders. Hence also the guidance on a dividend that Trond gave before. So speculating more into the future on potential metrics one day that would make you rebalance is very premature from my perspective.
Rasmus Errboe: Everything that I have seen, especially in Europe on the offshore wind side during the last 18 months, have only made me more confident in the attractiveness of the market going forward, while obviously continuing to have a razor-sharp focus on value and a very disciplined bidding on our side. If I look at the opportunities in all of our core markets, there are five, as an example, tenders coming up during the next 12 months, all with frameworks that make sense to us. Broadly speaking, there is ample opportunity for us to achieve sufficiently profitable growth for our shareholders. Hence also the guidance on a dividend that Trond gave before. So speculating more into the future on potential metrics one day that would make you rebalance is very premature from my perspective.
Speaker #1: So if I look at the opportunities in all of our core markets, there are sort of five, as an example, tenders coming up during the next 12 months.
Speaker #1: All with frameworks that make sense to us broadly speaking. There is ample opportunity for us to achieve sufficiently profitable growth for our shareholders. Hence also the guidance on dividend that Trond gave before.
Speaker #1: So sort of speculating more into the future on potential metrics one day that would make you make you rebalance is very premature from my perspective.
Speaker #3: That's clear. Thanks a lot, Rasmus.
Casper Blom: That is clear. Thanks a lot, Rasmus.
Casper Blom: That is clear. Thanks a lot, Rasmus.
Speaker #2: The next question comes from the line of Christian Torner from SAB. Please go ahead.
Operator: The next question comes from the line of Kristian Tornøe Johansen from SEB. Please go ahead.
Operator: The next question comes from the line of Kristian Tornøe Johansen from SEB. Please go ahead.
Speaker #3: Yes, thank you. I am just curious to get your view on the outcome of the Danish auction we saw recently. I mean, from my side, it's difficult to conclude anything else that Vattenfall was fairly aggressive in its bid.
Kristian Tornøe Johansen: Yes, thank you. I am just curious to get your view on the outcome of the Danish auction we saw recently. From my side, it is difficult to conclude anything else that Vattenfall was fairly aggressive in its bid. Obviously, this is interesting in regards to the comments you made several times, Rasmus, about value creation. So decentralized auction, do we need a change to competitive environment before you would actually be able to win capacity with the right value creation?
Kristian Tornøe Johansen: Yes, thank you. I am just curious to get your view on the outcome of the Danish auction we saw recently. From my side, it is difficult to conclude anything else that Vattenfall was fairly aggressive in its bid. Obviously, this is interesting in regards to the comments you made several times, Rasmus, about value creation. So decentralized auction, do we need a change to competitive environment before you would actually be able to win capacity with the right value creation?
Speaker #3: And obviously, this is interesting in regard to the comments you made several times, Rasmus, about value creation. So, decentralized auction—do we need a change to the competitive environment before you would actually be able to win capacity with the right value creation?
Speaker #1: Thanks, Christian. So first of all, when we look at new opportunities, new tenders, whether it's centralized tenders, proprietary tenders, or whether it's project-specific M&A, we obviously both look at the strategic fit.
Rasmus Errboe: Thanks, Kristian. First of all, when we look at new opportunities, new tenders, whether it is centralized tenders, proprietary tenders, or whether it is project-specific M&A, we obviously both look at the strategic fit for us, and we also look at value. Obviously, Denmark is one of our core markets, and it is an attractive market for offshore wind. The Danish politicians has, in many ways, provided a very good framework for the tenders. That being said, when you allocate capital of this magnitude, projects that are 5, 6 years before commissioning, after that, they will be there for, let us say, 30 years. You will obviously need to be very disciplined in your requirements to also value. We are, and that also goes for opportunities in Denmark.
Rasmus Errboe: Thanks, Kristian. First of all, when we look at new opportunities, new tenders, whether it is centralized tenders, proprietary tenders, or whether it is project-specific M&A, we obviously both look at the strategic fit for us, and we also look at value. Obviously, Denmark is one of our core markets, and it is an attractive market for offshore wind. The Danish politicians has, in many ways, provided a very good framework for the tenders. That being said, when you allocate capital of this magnitude, projects that are 5, 6 years before commissioning, after that, they will be there for, let us say, 30 years. You will obviously need to be very disciplined in your requirements to also value. We are, and that also goes for opportunities in Denmark.
Speaker #1: For us, and we also look at value. And obviously, Denmark is one of our core markets, and it is an attractive market for offshore wind.
Speaker #1: And the Danish politicians have in many ways provided a very good framework for the tenders. That being said, when you allocate capital of this magnitude to projects that are five, six years before commissioning, after that, they will be there for, let's say, 30 years.
Speaker #1: You would obviously need to be very disciplined in your requirements to also value. And we are and that also goes for opportunities in Denmark.
Speaker #1: As I said before, if there is one place I am bullish, it is on the prospects for being able to get to that profitability in our core markets in Europe.
Rasmus Errboe: As I said before, if there is one place I am bullish, it is on the prospects for being able to get to that profitability in our core markets in Europe. I am not going to speculate on the specific outcomes and bid levels in individual auctions. I focus on what we put forward ourselves, and I said we put forward a disciplined bid with a focus on value.
Rasmus Errboe: As I said before, if there is one place I am bullish, it is on the prospects for being able to get to that profitability in our core markets in Europe. I am not going to speculate on the specific outcomes and bid levels in individual auctions. I focus on what we put forward ourselves, and I said we put forward a disciplined bid with a focus on value.
Speaker #1: I'm not going to speculate on the specific outcomes and bid levels in individual auctions. That is, I focus on what we put forward ourselves.
Speaker #1: And I said we put forward a disciplined bid with a focus on value.
Speaker #3: Thank you.
Kristian Tornøe Johansen: Thank you.
Kristian Tornøe Johansen: Thank you.
Speaker #2: The next question comes from the line of Alberto Gandolfi from Goldman Sachs. Please go ahead.
Operator: The next question comes from the line of Alberto Gandolfi from Goldman Sachs. Please go ahead.
Operator: The next question comes from the line of Alberto Gandolfi from Goldman Sachs. Please go ahead.
Speaker #3: Oh, hi. Good afternoon. Thank you for taking my question. I am curious to see if you are willing to disclose how much is your work in progress.
Alberto Gandolfi: Oh, hi. Good afternoon. Thank you for taking my question. I am curious to see if you are willing to disclose how much is your work in progress. How much CapEx have you spent for assets that give zero contribution to your P&L and cash flow? One of the reason I am asking is I am trying to understand from a valuation perspective, but also your return on capital employed has an extremely conservative definition because you have all this CapEx spent with no contribution to the P&L. I am trying to understand how from about 6.5% you can go back to above 13%. If you could disclose that figure, it would be very helpful. Thank you so much.
Alberto Gandolfi: Oh, hi. Good afternoon. Thank you for taking my question. I am curious to see if you are willing to disclose how much is your work in progress. How much CapEx have you spent for assets that give zero contribution to your P&L and cash flow? One of the reason I am asking is I am trying to understand from a valuation perspective, but also your return on capital employed has an extremely conservative definition because you have all this CapEx spent with no contribution to the P&L. I am trying to understand how from about 6.5% you can go back to above 13%. If you could disclose that figure, it would be very helpful. Thank you so much.
Speaker #3: So how much capex have you spent for assets that give zero contribution to your P&L and cash flow? And one of the reasons I'm asking is I'm trying to understand from evaluation perspective, but also your return on capital employed has an extremely conservative definition because you have all these capex spent with no contribution to the P&L.
Speaker #3: So I'm trying to understand how from about six and a half percent you can go back to above 13%. And if you could disclose that figure, it would be very helpful.
Speaker #3: Thank you so much.
Speaker #1: We don't distinguish on our working capital level at that level Alberto. So there is I don't have a sort of a number in my head relative to how that sort of dead capital in our balance sheet relative to the return on capital employed.
Trond Westlie: Well, we do not distinguish on our working capital level at that level, Alberto. I do not have a number in my head relative to how that sort of dead capital in our balance sheet relative to the return on capital employed.
Trond Westlie: Well, we do not distinguish on our working capital level at that level, Alberto. I do not have a number in my head relative to how that sort of dead capital in our balance sheet relative to the return on capital employed.
Speaker #3: So can I try a logic to see if it makes any sense? Sorry, I didn't mean to interrupt.
Alberto Gandolfi: Can I try a logic to see if it makes any sense? Sorry, didn't mean to interrupt.
Alberto Gandolfi: Can I try a logic to see if it makes any sense? Sorry, didn't mean to interrupt.
Speaker #1: Yeah, I'm waiting.
Trond Westlie: I'm waiting.
Trond Westlie: I'm waiting.
Speaker #3: Sure. Thank you. And apologies about that. No, I was thinking that it takes two and a half, three years or sometimes longer to give the offshore.
Alberto Gandolfi: Thank you, and apologies about that. No, I was thinking that it takes 2.5, 3 years, or sometimes longer to build offshore. So if you have DKK 50, DKK 55 billion CapEx per annum, is it reasonable to assume that your work in progress is perhaps 12 to 18 months of CapEx, so I'm excluding onshore and so on. Would that be, you think, a crazy assumption on my side?
Alberto Gandolfi: Thank you, and apologies about that. No, I was thinking that it takes 2.5, 3 years, or sometimes longer to build offshore. So if you have DKK 50, DKK 55 billion CapEx per annum, is it reasonable to assume that your work in progress is perhaps 12 to 18 months of CapEx, so I'm excluding onshore and so on. Would that be, you think, a crazy assumption on my side?
Speaker #3: So, if you have $50 to $55 billion of capex per annum, is it reasonable to assume that your work in progress is perhaps 12 to 18 months of capex?
Speaker #3: So I'm excluding onshore and so on. Would that be, do you think, a crazy assumption on my side?
Speaker #1: I think that assumption is a bit sort of broad, in a sense, because that also depends on whether or not we have this construction agreement or, if you take Baltica 2, a 50-50 agreement.
Trond Westlie: I think that assumption is a bit broad in sense, because that also depends whether or not we have a construction agreement or if you take Baltica to a 50/50 agreement. On Sunrise, that would be right. For example, on Hornsea 3, it would not be right. We do have 100% of the CapEx in there, but part of the funding coming from our partner. So I would suggest that you take that discussion with the IR department, Alberto, to come closer on your logic.
Trond Westlie: I think that assumption is a bit broad in sense, because that also depends whether or not we have a construction agreement or if you take Baltica to a 50/50 agreement. On Sunrise, that would be right. For example, on Hornsea 3, it would not be right. We do have 100% of the CapEx in there, but part of the funding coming from our partner. So I would suggest that you take that discussion with the IR department, Alberto, to come closer on your logic.
Speaker #1: On sunrise, that would be right. On, for example, on Hornseat 3, it would not be right. We do have 100% of the capex in there, but part of the funding coming from our partner.
Speaker #1: So I would suggest that you take that discussion with the IR department, Alberto, to come closer on your logic.
Speaker #3: Thank you. Thank you for your patience, John. Thank you so much.
Alberto Gandolfi: Thank you. Thank you for your patience, Trond. Thank you so much.
Alberto Gandolfi: Thank you. Thank you for your patience, Trond. Thank you so much.
Operator: We now have a question from the line of Louis Bouillard from Oddo. Please go ahead.
Operator: We now have a question from the line of Louis Bouillard from Oddo. Please go ahead.
Speaker #2: We now have a question from the line of Louis Bouillard from Oddo. Please go ahead.
Speaker #3: Yes, hi. Good afternoon, and thank you for the presentation. Just wanting to bridge maybe a little bit the H2 EBITDA that should be expected considering your guidance for €28 billion.
Louis Bouillard: Yes. Hi, good afternoon, and thank you for the presentation. Just wanting to bridge maybe a little bit, H2 EBITDA that should be expected considering your guidance of DKK 28 billion. I understand and I appreciate that you feel quite comfortable with your guidance at the EBITDA level, but wanting to make sure that apparently, I would expect that you need to post your DKK 13 billion of EBITDA in the second half. It is to be compared to DKK 11 billion that you posted last year. We know that you have some commissioning that are expected, but at the same time, I think that some of these assets are supposed to already contribute at the moment because they are already very close to the commissioning date. So I would like to know if there is any sensitivity on your guidance potentially on the wind regime.
Louis Bouillard: Yes. Hi, good afternoon, and thank you for the presentation. Just wanting to bridge maybe a little bit, H2 EBITDA that should be expected considering your guidance of DKK 28 billion. I understand and I appreciate that you feel quite comfortable with your guidance at the EBITDA level, but wanting to make sure that apparently, I would expect that you need to post your DKK 13 billion of EBITDA in the second half. It is to be compared to DKK 11 billion that you posted last year. We know that you have some commissioning that are expected, but at the same time, I think that some of these assets are supposed to already contribute at the moment because they are already very close to the commissioning date. So I would like to know if there is any sensitivity on your guidance potentially on the wind regime.
Speaker #3: I understand and I appreciate that you feel quite comfortable with your guidance at ABDA level, but wanting to make sure that apparently I would expect that you need to post till 13 billion of ABDA in the second half.
Speaker #3: It's to be compared to 11 billion that you posted last year. We know that you have some commissioning that are expected, but at the same time, I think that some of these assets are supposed to already contribute at the moment because they're already very close to the commissioning date.
Speaker #3: So I would like to know if there is any sensitivity on your guidance potentially on the win regime. Do you think that eventually a relatively I would say low win regime in Q3, but most likely Q4 because Q3 is natural, would eventually put in jeopardy the guidance for this year?
Louis Bouillard: Do you think that eventually, relatively, I would say low wind regime in Q3, but most likely Q4 because Q3 is natural, would eventually put in jeopardy the guidance for this year? Thank you very much.
Louis Bouillard: Do you think that eventually, relatively, I would say low wind regime in Q3, but most likely Q4 because Q3 is natural, would eventually put in jeopardy the guidance for this year? Thank you very much.
Speaker #3: Thank you very much.
Speaker #1: When it comes to our guidance, you're absolutely correct, Louis. That the first half has been slightly better than we have expected. That is mostly due to the wind and price, but also as a negative element in specifically in the second quarter in bio, slight negative.
Trond Westlie: When it comes to our guidance, you are absolutely correct that the H1 has been slightly better than we had expected. That is mostly due to the wind and price, but also as a negative element in specifically in the Q2 in bio, a slight negative. When we do our guidance, we do guide on the average wind element. We do not set our guidance up relative to speculation about the wind elements. We do the guiding on the basis of the average. When it comes to the element, yes, we are in a good position to deliver on our 2026 guidance of more than 28. But there is also uncertainties relative to development and also some sort of percentage of completion elements, time elements, and other elements that is of a decent amount of uncertainty, and therefore, we are holding the more than 28 stable.
Trond Westlie: When it comes to our guidance, you are absolutely correct that the H1 has been slightly better than we had expected. That is mostly due to the wind and price, but also as a negative element in specifically in the Q2 in bio, a slight negative. When we do our guidance, we do guide on the average wind element. We do not set our guidance up relative to speculation about the wind elements. We do the guiding on the basis of the average. When it comes to the element, yes, we are in a good position to deliver on our 2026 guidance of more than 28. But there is also uncertainties relative to development and also some sort of percentage of completion elements, time elements, and other elements that is of a decent amount of uncertainty, and therefore, we are holding the more than 28 stable.
Speaker #1: When we do our guidance, we do guide on the average win element. So we do not sort of set our guidance up relative to speculation about the wind elements.
Speaker #1: We do the guiding on the basis of sort of the average. So when it comes to the element, yes, we are in a good position to deliver on our 26 guidance of more than 28.
Speaker #1: But there is also uncertainties relative to development and also some sort of percentage of completion elements, time elements, and other elements. That is of a decent amount of uncertainty.
Speaker #1: And therefore, we holding the more than 28 stable.
Speaker #3: Okay. Thank you for the clarification.
Louis Bouillard: Okay. Thank you for the clarification.
Louis Bouillard: Okay. Thank you for the clarification.
Speaker #2: The next question comes from the line of Dominic Nash from Barclays. Please go ahead.
Operator: The next question comes from the line of Dominic Nash from Barclays. Please go ahead.
Operator: The next question comes from the line of Dominic Nash from Barclays. Please go ahead.
Speaker #3: Good afternoon. Thank you for taking my question. Previously, I think you responded saying that you described offshore wind as a buyer's market when you were selling assets into it.
Dominic Nash: Good afternoon. Thank you for taking my question. Previously, I think you responded saying that you described offshore wind as a buyer's market when you were selling assets into it. But given the recent auction outcomes, particularly in the Danish, I think the 67 to 73 US megawatt hour, which I think is quite a low return. Is it now more attractive to acquire projects and seabed positions from third parties rather than bidding for them organically? On that, are you seeing a pipeline of potential attractive seabed leases or partially developed projects coming in as somehow big oil is reappraising its positions or some of the early expansion and exuberance we heard from three, four years ago starts to unwind? Where do you think the most compelling areas for this is? Thank you.
Dominic Nash: Good afternoon. Thank you for taking my question. Previously, I think you responded saying that you described offshore wind as a buyer's market when you were selling assets into it. But given the recent auction outcomes, particularly in the Danish, I think the 67 to 73 US megawatt hour, which I think is quite a low return. Is it now more attractive to acquire projects and seabed positions from third parties rather than bidding for them organically? On that, are you seeing a pipeline of potential attractive seabed leases or partially developed projects coming in as somehow big oil is reappraising its positions or some of the early expansion and exuberance we heard from three, four years ago starts to unwind? Where do you think the most compelling areas for this is? Thank you.
Speaker #3: But given the recent auction outcomes, particularly in the Danish, I think 67 to 73 euros megawatt hour, which I think is quite a low return, is it now more attractive to acquire projects and seed bed positions from third parties rather than sort of bidding for them organically?
Speaker #3: And on that, are you seeing a pipeline of potential attractive seed bed leases or partially developed projects coming in as something else of big oil is reappraising its positions or some of the early expansion and elubrance that we heard from sort of three, four years ago starts to unwind.
Speaker #3: And where do you think the most compelling areas for this is? Thank you.
Speaker #1: Thank you very much, Dominic. We see three avenues for growth for us. It is to centralize tenders. It is the proprietary auctions in the UK as an example.
Trond Westlie: Thank you very much, Dominic. We see three avenues for growth for us. It is the centralized tenders. It is the proprietary auctions in the UK as an example, Korea as an example, Australia as an example. Then we see what I choose to call project-specific M&A. So obviously not corporate M&A of any sense, but basically where you enter into a partnership with someone or entirely take over a project that has been won by others or developed by others in one shape or form, but well ahead of FID.
Trond Westlie: Thank you very much, Dominic. We see three avenues for growth for us. It is the centralized tenders. It is the proprietary auctions in the UK as an example, Korea as an example, Australia as an example. Then we see what I choose to call project-specific M&A. So obviously not corporate M&A of any sense, but basically where you enter into a partnership with someone or entirely take over a project that has been won by others or developed by others in one shape or form, but well ahead of FID.
Speaker #1: Korea as an example. Australia as an example. And then we see what I sort of choose to call project-specific M&A. So not obviously not corporate M&A of any sense, but basically where you enter into a partnership with someone or entirely take over a project that has been won by others or developed by others in one shape or form, but well ahead of FID.
Speaker #1: Those are the three avenues for growth that we are working with. And in a sense, it always has been, for as long as I can remember.
Rasmus Errboe: Those are the three avenues for growth that we are working with, and in a sense, it always have been for as long as I can remember. I am not going to speculate on or share my view on, as I said before, winning clearing levels at individual bits that can be in Denmark, it could have been in AR6, AR7, it can be in Poland. It is for all of us to just take a look at the numbers. What I can say is that we see a healthy balance starting to emerge in the market, both in my view, when it comes to competitiveness or competition between developers.
Rasmus Errboe: Those are the three avenues for growth that we are working with, and in a sense, it always have been for as long as I can remember. I am not going to speculate on or share my view on, as I said before, winning clearing levels at individual bits that can be in Denmark, it could have been in AR6, AR7, it can be in Poland. It is for all of us to just take a look at the numbers. What I can say is that we see a healthy balance starting to emerge in the market, both in my view, when it comes to competitiveness or competition between developers.
Speaker #1: I'm not going to I'm not going to speculate on or share my view on, as I said before, winning, clearing levels at individual bids that can be in Denmark.
Speaker #1: It could have been in AR6, AR7, it can be in Poland, it is for you or it is for all of us to just take a look at the numbers.
Speaker #1: What I can say is that we see a we see a healthy balance starting to emerge in the market, both in my view, when it comes to competitiveness or competition between developers there are fewer than what we saw three, four, five years ago where we also had a lot of oil majors in the mix.
Rasmus Errboe: There are fewer than what we saw three, four, five years ago, where we also had a lot of oil majors in the mix, and there are predominantly companies that sort of have significant experience working with offshore wind and therefore also typically looking at the projects through the same lens. What is very important from a competition perspective is to ensure that we have frameworks that allow competition to play out. That is what we continue, that is the discussion we continue to have with the regulators across Europe, that you allow competition to play out like you just saw in the Danish tender where you had five bidders for Hesselø and you had two bidders for the North Sea, because that allows a healthy competition.
Rasmus Errboe: There are fewer than what we saw three, four, five years ago, where we also had a lot of oil majors in the mix, and there are predominantly companies that sort of have significant experience working with offshore wind and therefore also typically looking at the projects through the same lens. What is very important from a competition perspective is to ensure that we have frameworks that allow competition to play out. That is what we continue, that is the discussion we continue to have with the regulators across Europe, that you allow competition to play out like you just saw in the Danish tender where you had five bidders for Hesselø and you had two bidders for the North Sea, because that allows a healthy competition.
Speaker #1: And there are predominantly companies that sort of have significant experience working with all offshore wind and therefore also typically looking at the projects in a sort of through the same lens.
Speaker #1: What is very important from a competition perspective is to ensure that we have frameworks that allow competition to play out. And that is what we continue the sort of that's the discussion we continue to have with the regularators across Europe, that you allow competition to play out like you just saw in the Danish tender where you had one bidder for Hesselø sorry, five bidders for Hesselø and you had two bidders for the North Sea.
Speaker #1: Because that allows a healthy competition. So of course, you should take that comment also in the context of the sort of draft regulatory frameworks that we are seeing in many of our core markets, including in Germany.
Rasmus Errboe: So of course, you should take that comment also in the context of the sort of draft regulatory frameworks that we are seeing in many of our core markets, including in Germany. On the M&A side, I am not going to be more specific. We see a healthy balance. We see several opportunities coming to market, and we assess what comes, and we have three avenues of growth.
Rasmus Errboe: So of course, you should take that comment also in the context of the sort of draft regulatory frameworks that we are seeing in many of our core markets, including in Germany. On the M&A side, I am not going to be more specific. We see a healthy balance. We see several opportunities coming to market, and we assess what comes, and we have three avenues of growth.
Speaker #1: On the M&A side, I'm not going to be more specific. We see a healthy balance. We see several opportunities coming to market, and we assess what comes. We have three avenues, of course.
Speaker #3: Thank you.
Dominic Nash: Thank you.
Dominic Nash: Thank you.
Speaker #2: The next question comes from the line of Harry Riebert from. BNP Paribas? Please go ahead.
Operator: The next question comes from the line of Harry Sherbet from BNP Paribas. Please go ahead.
Operator: The next question comes from the line of Harry Sherbet from BNP Paribas. Please go ahead.
Speaker #3: Hi everyone. Thanks for taking my questions, Harris. Hi Trent. So my question singular. I wanted to ask get into a bit of the detail on the German offshore wind auctions.
Harry Sherbet: Hi, everyone. Thanks for taking my questions. Hi, Rasmus. Hi, Trond. Sorry, my question singular. I wanted to ask, get into a bit of detail on the German offshore wind auctions. The government's released the framework, the two-stage framework. Is that framework sufficient given the push by you and the industry for more CFD structured auctions, and is that an auction framework that you think you could work with and would be a good template for other countries to adopt in Europe? Thank you.
Harry Wyburd: Hi, everyone. Thanks for taking my questions. Hi, Rasmus. Hi, Trond. Sorry, my question singular. I wanted to ask, get into a bit of detail on the German offshore wind auctions. The government's released the framework, the two-stage framework. Is that framework sufficient given the push by you and the industry for more CFD structured auctions, and is that an auction framework that you think you could work with and would be a good template for other countries to adopt in Europe? Thank you.
Speaker #3: So, the government released the framework of the two-stage framework. Is that framework sufficient, given the push by you and the industry for more CFD-structured auctions?
Speaker #3: And is that an auction framework that you think you could work with and would be a good template for other countries to adopt in Europe?
Speaker #3: Thank you.
Speaker #1: Thank you very much, Harry. So as I have said before, in terms of templates, I think the approach to tendering out offshore wind that we see in the UK remains a very good model.
Rasmus Errboe: Thank you very much, Harry. As I have said before, in terms of templates, I think the approach to tendering out offshore wind that we see in the UK remains a very good model. When I look at the latest draft framework that we very recently received from the Federal Ministry for Economic Affairs and Energy, there are clearly highlights in that. It is encouraging for me to see that the expansion targets for offshore wind remain unchanged in Germany, so 30 gigawatts by 2030, 40 gigawatts by 2035, and 70 gigawatts by 2045. I am also encouraged by the fact that it is a return to two-way CFDs. That was, in our view, about time. To be a bit blunt, in Germany, it is a very attractive market for offshore wind, and we are very pleased to see the return to two-sided CFDs.
Rasmus Errboe: Thank you very much, Harry. As I have said before, in terms of templates, I think the approach to tendering out offshore wind that we see in the UK remains a very good model. When I look at the latest draft framework that we very recently received from the Federal Ministry for Economic Affairs and Energy, there are clearly highlights in that. It is encouraging for me to see that the expansion targets for offshore wind remain unchanged in Germany, so 30 gigawatts by 2030, 40 gigawatts by 2035, and 70 gigawatts by 2045. I am also encouraged by the fact that it is a return to two-way CFDs. That was, in our view, about time. To be a bit blunt, in Germany, it is a very attractive market for offshore wind, and we are very pleased to see the return to two-sided CFDs.
Speaker #1: When I look at, basically, the latest draft framework that we very recently received from the German Ministry of Economic Affairs and Energy, there are clearly highlights in that.
Speaker #1: It is encouraging for me to see that the expansion targets for offshore wind remain unchanged in Germany. So 30 gigawatts by 2030, 40 gigawatts by 2035, and 70 gigawatts by 2045.
Speaker #1: I'm also encouraged by the fact that it is a return to CFDs—to two-way CFDs. That was, in our view, sort of about time, to be a bit blunt, in Germany.
Speaker #1: It's a very attractive market for offshore wind, and we are very pleased to see the return to two-sided CFDs. There are always mechanics in frameworks that can—sort of—where we would have done it differently.
Rasmus Errboe: There are always mechanics in frameworks where we would have done it differently, and we will take that in the dialogue we have as part of the market hearing. I think that is the best forum for that. I am not going to comment on the caps of EUR 94 and EUR 96 with an opportunity to increase with up to 35%. I am just going to leave that uncommented for now. But just overall say that we are pleased with the direction of travel that we see in Germany.
Rasmus Errboe: There are always mechanics in frameworks where we would have done it differently, and we will take that in the dialogue we have as part of the market hearing. I think that is the best forum for that. I am not going to comment on the caps of EUR 94 and EUR 96 with an opportunity to increase with up to 35%. I am just going to leave that uncommented for now. But just overall say that we are pleased with the direction of travel that we see in Germany.
Speaker #1: And we will take that in the dialogue we have as part of the market hearing. I think that is the best forum for that.
Speaker #1: I'm not going to comment on the caps of 94 euros and 96 euros with an opportunity to increase with up to 35%. I'm just going to leave that on commented for now.
Speaker #1: But just overall say that we are pleased with the direction of travel that we see in Germany.
Speaker #3: Okay. Thank you very much.
Harry Sherbet: Okay. Thank you very much.
Harry Wyburd: Okay. Thank you very much.
Operator: The next question comes from the line of Ahmed Farman from Jefferies. Please go ahead.
Operator: The next question comes from the line of Ahmed Farman from Jefferies. Please go ahead.
Speaker #2: The next question comes from the line of Ahmed Farman from Jefferies. Please go ahead.
Speaker #3: Yes. Thank you. Trent, maybe this is a question for you. I was just wondering whether we can get an update from you on the dynamics of the ITC market in the US.
Ahmed Farman: Yes, thank you. Trond, maybe this is a question for you. I was just wondering whether we can get an update from you on the dynamics of the ITC market in the US. Obviously, we have seen some seabed leases since then. Your projects have moved further. And as you are highlighting today, they are progressing according to plan. So I just wanted to see if anything that has either changed your view or anything you see in the market in terms of the broader health of the market and monetization of ITCs. Thank you.
Ahmed Farman: Yes, thank you. Trond, maybe this is a question for you. I was just wondering whether we can get an update from you on the dynamics of the ITC market in the US. Obviously, we have seen some seabed leases since then. Your projects have moved further. And as you are highlighting today, they are progressing according to plan. So I just wanted to see if anything that has either changed your view or anything you see in the market in terms of the broader health of the market and monetization of ITCs. Thank you.
Speaker #3: Obviously, we have seen some seabed leases since then. Your projects have moved further. And as you sort of highlighting today, they are progressing according to plan.
Speaker #3: So I just wanted to see if anything that has either changed your view or anything you see in the market in terms of the broader health of the market and monetization of ITCs.
Speaker #3: Thank you.
Speaker #1: When it comes to the sort of the tax credit process, as I said in the last quarter, we have established the structure. The advisors so moving along on time elements of the structure on the tax credits.
Trond Westlie: When it comes to the tax credit process, as I said in the last quarter, we have established the structure, the advisors, so moving along on time elements of the structure on the tax credits. The development from last quarter is that the markets itself have become slightly more positive relative to certain areas of the US business doing better that are used to using the tax credits. So the marketing phase of the tax credits has been slightly better than what we had planned for. When it comes to Revolution, that is in good progress. When it comes to Sunrise, that marketing process has not started yet.
Trond Westlie: When it comes to the tax credit process, as I said in the last quarter, we have established the structure, the advisors, so moving along on time elements of the structure on the tax credits. The development from last quarter is that the markets itself have become slightly more positive relative to certain areas of the US business doing better that are used to using the tax credits. So the marketing phase of the tax credits has been slightly better than what we had planned for. When it comes to Revolution, that is in good progress. When it comes to Sunrise, that marketing process has not started yet.
Speaker #1: So the development from last quarter is that the market itself have become slightly more positive relative to certain areas of the US business is doing better.
Speaker #1: That are used to using the tax credits. So the marketing phase of the tax credits has been slightly better. Than what we had planned for.
Speaker #1: So when it comes to Revolution, that is in good progress. When it comes to Sunrise, that marketing process has not started yet. So we are in the process of assembling the structure on Sunrise and also doing the administration—sort of the back office work—to get it established in the right fashion.
Trond Westlie: We are in the process of assembling the structure on Sunrise and also doing the administration and sort of the back office work to get it established in the right fashion, so that when it comes to the marketing elements on Sunrise, that has not started. But Revolution is going well ahead.
Trond Westlie: We are in the process of assembling the structure on Sunrise and also doing the administration and sort of the back office work to get it established in the right fashion, so that when it comes to the marketing elements on Sunrise, that has not started. But Revolution is going well ahead.
Speaker #1: So when it comes to the marketing elements on Sunrise, that has not started. But Revolution is going well ahead.
Speaker #3: So can I ask just a quick follow-up? When do you expect the marketing process on sunrise to start? Thank you.
Ahmed Farman: Can I ask just a quick follow-up? When do you expect the marketing process on Sunrise to start? Thank you.
Ahmed Farman: Can I ask just a quick follow-up? When do you expect the marketing process on Sunrise to start? Thank you.
Speaker #1: The likelihood of that starting is not until beginning of 2027.
Trond Westlie: The likelihood of that starting is not until beginning of 2027.
Trond Westlie: The likelihood of that starting is not until beginning of 2027.
Speaker #3: Thank you.
Ahmed Farman: Thank you.
Ahmed Farman: Thank you.
Speaker #2: We now have a question from the line of Ollie Jefferies from Deutsche Bank. Please go ahead.
Operator: We now have a question from the line of Olly Jeffery from Deutsche Bank. Please go ahead.
Operator: We now have a question from the line of Olly Jeffery from Deutsche Bank. Please go ahead.
Speaker #3: Thanks very much. And good afternoon. My question is around we think about your EBITDA towards the end of this decade when you finish constructing projects.
Olly Jeffery: Thanks very much. Good afternoon. My question is around, we think about your EBITDA towards the end of this decade when you finish construction projects that you currently have on your books, and then there being a bit of a gap until you potentially have new projects. You potentially could be involved in auctions in Belgium and the Netherlands later this year. My understanding the COD for those is potentially 2031, 2032. I would just be keen to get your sense of how long a gap would you be willing to tolerate a kind of flattish EBITDA growth from absence of new projects? Or would you look to more try and look in the M&A market on a project basis to try and bridge some of that gap? Your thoughts on that would be great. Thank you.
Olly Jeffery: Thanks very much. Good afternoon. My question is around, we think about your EBITDA towards the end of this decade when you finish construction projects that you currently have on your books, and then there being a bit of a gap until you potentially have new projects. You potentially could be involved in auctions in Belgium and the Netherlands later this year. My understanding the COD for those is potentially 2031, 2032. I would just be keen to get your sense of how long a gap would you be willing to tolerate a kind of flattish EBITDA growth from absence of new projects? Or would you look to more try and look in the M&A market on a project basis to try and bridge some of that gap? Your thoughts on that would be great. Thank you.
Speaker #3: You currently have on your books. And then they're being a bit of a gap. So you potentially have new projects. You potentially could be involved in auctions in Belgium and the Netherlands later this year.
Speaker #3: My understanding the COD for those is potentially 31, 2032. So just be keen to kind of get your sense of how long a gap would you be willing to tolerate to kind of flatish EBITDA growth in absence of new projects?
Speaker #3: Or would you look to more try and look in the M&A market on a project basis to try and bridge some of that gap? And your thoughts on that would be great.
Speaker #3: Thank you.
Speaker #1: Thanks a lot, Ollie. Absolutely. So if we just take one step back first and just look at our growth profile. Right now, as we have also discussed today, we remain on track to deliver on our guidance for this year of EBITDA of more than 28.
Rasmus Errboe: Thanks a lot, Olly. Absolutely. So if we just take one step back first and just look at our growth profile. Right now, as we have also discussed today, we remain on track to deliver on our guidance for this year of EBITDA of more than DKK 28 billion. And we have a guidance for next year of an EBITDA of more than DKK 32 billion. We delivered a little bit more than DKK 25 billion last year. In other words, the growth that we are seeing right now on our EBITDA, in 2026 and 2027, expectedly, is very, very significant. It is sort of +10% growth, at least, especially a bit more next year, across both years.
Rasmus Errboe: Thanks a lot, Olly. Absolutely. So if we just take one step back first and just look at our growth profile. Right now, as we have also discussed today, we remain on track to deliver on our guidance for this year of EBITDA of more than DKK 28 billion. And we have a guidance for next year of an EBITDA of more than DKK 32 billion. We delivered a little bit more than DKK 25 billion last year. In other words, the growth that we are seeing right now on our EBITDA, in 2026 and 2027, expectedly, is very, very significant. It is sort of +10% growth, at least, especially a bit more next year, across both years.
Speaker #1: And we have given guidance for next year of an EBITDA of more than $32 million. We delivered a little bit more than $25 million last year.
Speaker #1: In other words, the growth that we are seeing right now on our EBITDA in 2026 and 2027 expectedly is very, very significant. It is sort of plus 10% growth at least, especially a bit more next year, across both years.
Speaker #1: So we are looking at a few years now where we are on the back of sort of executing on our 8.1 gigawatt construction sort of program, which is a lot.
Rasmus Errboe: We are looking at a few years now where we are on a back of executing on our 8.1 gigawatt construction program, which is a lot, and also more than I would expect we would have any time soon in the future. We are seeing very significant growth. Relative to that, you are of course right that our growth will, in the most relevant scenarios, flatten, in the years on the other side, so the back end of this decade. That being said, as I have said a few times, if there is anywhere where I am bullish, it is for the long-term prospects and mid to long-term projects for offshore wind in Europe.
Rasmus Errboe: We are looking at a few years now where we are on a back of executing on our 8.1 gigawatt construction program, which is a lot, and also more than I would expect we would have any time soon in the future. We are seeing very significant growth. Relative to that, you are of course right that our growth will, in the most relevant scenarios, flatten, in the years on the other side, so the back end of this decade. That being said, as I have said a few times, if there is anywhere where I am bullish, it is for the long-term prospects and mid to long-term projects for offshore wind in Europe.
Speaker #1: And also more than I would expect we would have anytime soon in the future. We are seeing very significant growth. Relative to that, you are of course right that our growth will in most relevant scenarios flatten.
Speaker #1: In the years on the other side, so the back end of this decade. That being said, as I have said a few times, if there is anywhere where I'm bullish, it is for the long-term prospects and mid to long-term projects for offshore wind in Europe.
Speaker #1: And if we just take, sort of, the bucket of growth that I've talked about before, which is decentralized tenders, that's the easiest one to talk to in this regard.
Rasmus Errboe: If we just take the bucket of growth that I have talked about before, which is the centralized tenders, that are the easiest one to talk to in this regard, then you are very much seeing potential CODs in the early 2030s in many of the opportunities that could potentially be relevant. If you just look at the tenders that are coming, look at it factually without reading anything into where we may or may not be. The Netherlands, Belgium, Germany, the UK, and Taiwan are five countries where there are tenders coming up the next 12 months. All of those projects, plus minus, will be with CODs in the early 2030s, roughly, again, plus minus, on the same timeline as we saw for the Danish bids.
Rasmus Errboe: If we just take the bucket of growth that I have talked about before, which is the centralized tenders, that are the easiest one to talk to in this regard, then you are very much seeing potential CODs in the early 2030s in many of the opportunities that could potentially be relevant. If you just look at the tenders that are coming, look at it factually without reading anything into where we may or may not be. The Netherlands, Belgium, Germany, the UK, and Taiwan are five countries where there are tenders coming up the next 12 months. All of those projects, plus minus, will be with CODs in the early 2030s, roughly, again, plus minus, on the same timeline as we saw for the Danish bids.
Speaker #1: Then you are very much seeing potential CODs in the early 30s in many of the opportunities that could potentially be relevant. So if you look at sort of just look at the tenders that are coming, just look at it factually without reading anything into where we may or may not be.
Speaker #1: The Netherlands, Belgium, Germany, the UK, and Taiwan, are five countries where there are tenders coming up the next 12 months. All of those projects plus minors will be with CODs in the early 30s sort of roughly again plus minus on the same timeline as we saw for the Danish bids.
Speaker #1: So there is a lot of opportunity out there still. And we remain very confident and very convinced that we will get our fair share of the profitable growth.
Rasmus Errboe: There is a lot of opportunity out there still, and we remain very confident and very convinced that we will get our fair share of the profitable growth. In terms of managing the gap as you mentioned before, there is not a scenario where we will sacrifice value in our capital allocation to fuel the machine, if you will. Of course, this challenge is not new to us. This was part of our strategic thinking also last year. We have mapped our capabilities throughout the entire organization. We have a very firm view on how we will manage those years. Again, it is very subject to outcome of tenders Proprietary and centralized, and also potential project-specific M&A. This is the long game, and we are convinced about the mid to long-term growth for Ørsted.
Rasmus Errboe: There is a lot of opportunity out there still, and we remain very confident and very convinced that we will get our fair share of the profitable growth. In terms of managing the gap as you mentioned before, there is not a scenario where we will sacrifice value in our capital allocation to fuel the machine, if you will. Of course, this challenge is not new to us. This was part of our strategic thinking also last year. We have mapped our capabilities throughout the entire organization. We have a very firm view on how we will manage those years. Again, it is very subject to outcome of tenders Proprietary and centralized, and also potential project-specific M&A. This is the long game, and we are convinced about the mid to long-term growth for Ørsted.
Speaker #1: In terms of sort of managing the gap as you are mentioned before, there is not a scenario where we will sacrifice value in our capital allocation to sort of fuel the machine, if you will.
Speaker #1: We have of course this challenge is not new to us. We have this was part of our strategic thinking also last year. We have mapped our capabilities throughout the entire organization.
Speaker #1: We have a very firm view on how we will manage those years. And again, it is very subject to the outcome of tenders, proprietary and centralized, and also potential project-specific M&A.
Speaker #1: This is the long game. And we are convinced about mid to long-term growth first.
Speaker #2: We have now a question from the line of Peter Bistiga from Bank of America. Please go ahead.
Operator: We have now a question from the line of Peter Bisztyga from Bank of America. Please go ahead.
Operator: We have now a question from the line of Peter Bisztyga from Bank of America. Please go ahead.
Speaker #3: Hi. Good afternoon. Thanks for taking my question. Maybe sort of following on from that previous question, you've previously mentioned that you've got six or seven gigawatts of safe harbored equipment for onshore wind, solar, and other technologies.
Peter Bisztyga: Hi. Good afternoon, and thanks for taking my question. Maybe following on from that previous question. You have previously mentioned that you have got 6 or 7 gigawatts of safe harbored equipment for onshore wind, solar, and other technologies, I guess, BESS, I guess, in the US. I think on the previous call, you mentioned that some of those projects could be advanced towards FID. Just wondering, what is the status of that endeavor, and why do you not see the US onshore business as potentially one of the things that could help bridge this kind of growth air pocket, as people like to call it, in the last part of this decade? Thank you.
Peter Bisztyga: Hi. Good afternoon, and thanks for taking my question. Maybe following on from that previous question. You have previously mentioned that you have got 6 or 7 gigawatts of safe harbored equipment for onshore wind, solar, and other technologies, I guess, BESS, I guess, in the US. I think on the previous call, you mentioned that some of those projects could be advanced towards FID. Just wondering, what is the status of that endeavor, and why do you not see the US onshore business as potentially one of the things that could help bridge this kind of growth air pocket, as people like to call it, in the last part of this decade? Thank you.
Speaker #3: I guess BESS, I guess. In the US, and I'm just sort of—and I think on the previous call, you sort of mentioned that some of those projects could be advanced towards FID.
Speaker #3: Just sort of wondering what is the status of that endeavor? And why do you not see sort of a US onshore business as potentially one of the things that could help bridge this kind of growth air pocket as people like to call it?
Speaker #3: In the last part of this decade. Thank you.
Speaker #1: Thank you very much, Peter. We have as you also referenced, we have a solid pipeline development pipeline of opportunities in our US onshore business for the years to come.
Rasmus Errboe: Thank you very much, Peter. We have, as you also referenced, we have a solid development pipeline of opportunities in our US onshore business for the years to come. We have 6 to 7 gigawatts of capacity that meet the IRS definition of qualifications through 2029. Our development portfolio consists of a mix of solar, wind, and also storage. I would say our near-term portfolio is probably weighted more towards solar. We recently achieved COD on all 300 BESS, so 250-megawatt battery in Texas. We also COD Badger Wind in Q1. So we continue to grow our US onshore business, and it is going well. The fundamentals for onshore and US are good, as has also been widely referenced in the market.
Rasmus Errboe: Thank you very much, Peter. We have, as you also referenced, we have a solid development pipeline of opportunities in our US onshore business for the years to come. We have 6 to 7 gigawatts of capacity that meet the IRS definition of qualifications through 2029. Our development portfolio consists of a mix of solar, wind, and also storage. I would say our near-term portfolio is probably weighted more towards solar. We recently achieved COD on all 300 BESS, so 250-megawatt battery in Texas. We also COD Badger Wind in Q1. So we continue to grow our US onshore business, and it is going well. The fundamentals for onshore and US are good, as has also been widely referenced in the market.
Speaker #1: We have a six to seven gigawatts of definition of qualification through 29. And our development portfolio consists of a mix of solar, wind, and also storage.
Speaker #1: And I would say near-term, our near-term portfolio is probably weighted more towards solar. We recently achieved COD on all 300 BESS. So 250 megawatt battery in Texas.
Speaker #1: And we also COD Badger Wind in Q1, so we continue to grow our US onshore business, and it's going well. The fundamentals for onshore in the US are good, as has also been widely referenced in the market.
Rasmus Errboe: In terms of our strategic direction, it is, as I have said before, our key focus in our capital allocation will be on offshore wind, predominantly in Europe. Nothing has changed in that regard. As I also have said, I am more convinced than for a very long time about the prospects for offshore wind in Europe when I look at what has happened the last 18 months. We have separated our US onshore business out, running it as a separate entity, finalized that last year, and it is going really well. We have a solid business, we have growth opportunities, and the team is delivering really well.
Rasmus Errboe: In terms of our strategic direction, it is, as I have said before, our key focus in our capital allocation will be on offshore wind, predominantly in Europe. Nothing has changed in that regard. As I also have said, I am more convinced than for a very long time about the prospects for offshore wind in Europe when I look at what has happened the last 18 months. We have separated our US onshore business out, running it as a separate entity, finalized that last year, and it is going really well. We have a solid business, we have growth opportunities, and the team is delivering really well.
Speaker #1: In terms of our strategic direction, it is, as I have said before, our key focus in our capital allocation will be on offshore wind, predominantly in Europe.
Speaker #1: Nothing has changed in that regard. As I also have said, I am more convinced than for a very long time about the prospects for offshore wind in Europe when I look at what has happened the last 18 months.
Speaker #1: We have separated our US onshore business out in a running in a sort of a separate entity finalized that last year. And it's going really well.
Speaker #1: And we have a solid business. We have growth opportunities. And the team is delivering really well.
Speaker #3: Okay. So maybe sorry, just to follow up. I mean, is it reasonable to assume that we could have some contribution from that US onshore pipeline within the next two, three, four years?
Peter Bisztyga: Okay. So maybe, sorry, just to follow up. Is it reasonable to assume that we could have some contribution from that US onshore pipeline within the next 2, 3, 4 years?
Peter Bisztyga: Okay. So maybe, sorry, just to follow up. Is it reasonable to assume that we could have some contribution from that US onshore pipeline within the next 2, 3, 4 years?
Rasmus Errboe: We have an organization. We do not guide on volume, as you know. We guide on values. I am not going to throw out gigawatt ambitions or targets per year, also not for the US onshore business. But we have a pipeline, and we have a team, and we have an organization that has opportunity to grow in the coming years.
Rasmus Errboe: We have an organization. We do not guide on volume, as you know. We guide on values. I am not going to throw out gigawatt ambitions or targets per year, also not for the US onshore business. But we have a pipeline, and we have a team, and we have an organization that has opportunity to grow in the coming years.
Speaker #1: We have an organization. We don't guide on volume, as you know. We guide on value. So I'm not going to throw out gigawatt ambitions or targets per year, also not for the US onshore business.
Speaker #1: But we have a pipeline, and we have a team, and we have an organization that has opportunity to grow in the coming years.
Speaker #3: Okay. Thank you very much.
Peter Bisztyga: Okay. Thank you very much.
Peter Bisztyga: Okay. Thank you very much.
Operator: Next question from the line of Jenny Ping from Citi. Please go ahead.
Operator: Next question from the line of Jenny Ping from Citi. Please go ahead.
Speaker #2: Next question from the line of Jenny Ping from City. Please go ahead.
Speaker #4: Thank you very much, for the opportunity. A couple of operational related questions, please. If I look at the Changhua 2B and 4 projects in terms of progress, you are still quite far out 22 out, I think, from being able to fully energize and the progress versus 1Q seems to be quite slow relative to what you have achieved previously.
Jenny Ping: Thank you very much for the opportunity. Couple of operational related questions, please. If I look at the Changhua 2B and 4 projects in terms of progress, you are still quite far out, 2022 out, I think, from being able to fully energize. The progress versus Q1 seems to be quite slow relative to what you have achieved previously. I just wondered whether there is anything to read into there. Separately, looking at Revolution, you have installed incrementally, I think, one turbine within the last quarter. But obviously, I guess the majority of the effort has been going on to energizing and powering what you have. Is there any hold up in terms of vessels on the last few installations? Just lastly, on Hornsea 3, what is the latest around the sort of progress with National Grid in order to hit the target?
Jenny Ping: Thank you very much for the opportunity. Couple of operational related questions, please. If I look at the Changhua 2B and 4 projects in terms of progress, you are still quite far out, 2022 out, I think, from being able to fully energize. The progress versus Q1 seems to be quite slow relative to what you have achieved previously. I just wondered whether there is anything to read into there. Separately, looking at Revolution, you have installed incrementally, I think, one turbine within the last quarter. But obviously, I guess the majority of the effort has been going on to energizing and powering what you have. Is there any hold up in terms of vessels on the last few installations? Just lastly, on Hornsea 3, what is the latest around the sort of progress with National Grid in order to hit the target?
Speaker #4: I just wondered whether there's anything to read into there. And then separately, looking at revolution, you've installed incrementally, I think, one turbine within the last quarter, but obviously, I guess the majority of the effort has been going on to energizing and powering what you have.
Speaker #4: Is there any holdup in terms of vessels on the last few installation? And then just lastly, on Hornsea 3, what's the latest around the sort of progress with National Grid in order to hit the target, if you can give us a little bit of detail there, that would be great.
Jenny Ping: If you can give us a little bit of detail there, that would be great. Thank you.
Jenny Ping: If you can give us a little bit of detail there, that would be great. Thank you.
Speaker #4: Thank you.
Speaker #1: Absolutely, Jenny. Thanks a lot. So if we take them one by one, Changhua, Changhua first, or let me lift it up quickly before all of the three projects that you referenced, so Changhua 2B and 4 Revolution and Hornsea 3 are moving forward according to plan.
Rasmus Errboe: Absolutely, Jenny. Thanks a lot. If we take them one by one, Changhua first, or let me lift it up quickly before. All of the three projects that you referenced, so Changhua 2B and 4, Revolution, and Hornsea 3 are moving forward according to plan, both on schedule and also on cost, just to be very clear. If we take Changhua first, the degree of completion is now 85%. We have achieved first power on all turbines on Changhua 4. As you remember, the key focus for us has been on Changhua 2B on the export cable. Changhua 2B is 24 out of the 66 turbines, and Changhua 4 is only two of the 66 turbines.
Rasmus Errboe: Absolutely, Jenny. Thanks a lot. If we take them one by one, Changhua first, or let me lift it up quickly before. All of the three projects that you referenced, so Changhua 2B and 4, Revolution, and Hornsea 3 are moving forward according to plan, both on schedule and also on cost, just to be very clear. If we take Changhua first, the degree of completion is now 85%. We have achieved first power on all turbines on Changhua 4. As you remember, the key focus for us has been on Changhua 2B on the export cable. Changhua 2B is 24 out of the 66 turbines, and Changhua 4 is only two of the 66 turbines.
Speaker #1: Both on schedule and also on cost, just to be very clear. If we take Changhua first, the degree of completion is now 85%. We have achieved the first power on all turbines on Changhua 4.
Speaker #1: As you remember, the key focus for us has been on Changhua ua 2B. On the export cable, so Changhua 2B is 24 out of the 66 turbines and Changhua 4 is 42 of the 66 turbines.
Speaker #1: But on 2B, our focus has been on repairing the export cable. And that is what is, as we have said last time, also is pushing us to the back end of Q3 in terms of COD.
Rasmus Errboe: But on 2B, our focus has been on repairing the export cable, and that is what is, as we have said last time also, is pushing us to the back end of Q3 in terms of COD. That was predominantly a focus around getting the vessel on-site. Everything is going according to plan in that regard. The Calypso vessel, it is called, from Van Oord, is now on-site. We are actually fixing the joint on the export cable as we speak. It's always at this point, this time of year in Taiwan, you have the typhoon season. So there is also sort of a bit of a focus on the weather windows. This week it looks good. So we are active right now. Then we expect to energize the cable very soon.
Rasmus Errboe: But on 2B, our focus has been on repairing the export cable, and that is what is, as we have said last time also, is pushing us to the back end of Q3 in terms of COD. That was predominantly a focus around getting the vessel on-site. Everything is going according to plan in that regard. The Calypso vessel, it is called, from Van Oord, is now on-site. We are actually fixing the joint on the export cable as we speak. It's always at this point, this time of year in Taiwan, you have the typhoon season. So there is also sort of a bit of a focus on the weather windows. This week it looks good. So we are active right now. Then we expect to energize the cable very soon.
Speaker #1: And that was predominantly a focus around getting the vessel on site. And everything is going according to plan in that regard. The Calypso vessel, it is called, from Fernord, is now on site.
Speaker #1: And we are they are actually we actually fixing the joint on the export cable as we speak. It's always, at this point, this time of year in Taiwan, you have the typhoon season, so it's also sort of a bit of a focus on the weather windows.
Speaker #1: And this week, it looks good. So we are active right now, and then we expect to energize the cable very soon. On the back of that, we need to commission the remaining 24 turbines on Changhua 2B that have been installed.
Rasmus Errboe: Then on the back of that, we need to commission the remaining 24 turbines on Changhua 2B that have been installed. So we're working hard. The team is doing an excellent job. But we are moving forward according to plan, and we expect COD at the back end of Q3. On Revolution Wind, the degree of completion is 95%. Of course, if you compare it with the 94 of last quarter, of course, it's not that I don't understand your question. We are now at 61 turbines installed. But just as a reminder, we basically stopped turbine installation on Revolution Wind earlier in the year and moved the vessel Scylla from CTX to Sunrise. That vessel has now installed 20 turbines on Sunrise, and that's going quite well.
Rasmus Errboe: Then on the back of that, we need to commission the remaining 24 turbines on Changhua 2B that have been installed. So we're working hard. The team is doing an excellent job. But we are moving forward according to plan, and we expect COD at the back end of Q3. On Revolution Wind, the degree of completion is 95%. Of course, if you compare it with the 94 of last quarter, of course, it's not that I don't understand your question. We are now at 61 turbines installed. But just as a reminder, we basically stopped turbine installation on Revolution Wind earlier in the year and moved the vessel Scylla from CTX to Sunrise. That vessel has now installed 20 turbines on Sunrise, and that's going quite well.
Speaker #1: So everything we're working hard. The team is doing an excellent job. But we are moving forward according to plan. And we expect COD at the back end of Q3.
Speaker #1: On revolution wind, the degree of completion is 95%. And of course, if you compare it with the 94 of last quarter, of course, it's not that I don't understand your question.
Speaker #1: We are now at 61 turbines installed. But just as a reminder, we basically stopped a turbine installation on revolution wind earlier in the year and moved the vessel Scilla from CGX to Sunrise.
Speaker #1: And that vessel has now installed 20 turbines on Sunrise. And that's going quite well. And now we have returned the vessel to revolution. And it has now installed one of the remaining five turbines.
Rasmus Errboe: We have now returned the vessel to Revolution, and it has now installed one of the remaining 5 turbines, so we are at 61. We expect to install the remaining in Revolution in the coming weeks and months. Therefore, also here, moving forward according to plan and the vast majority of the 65 turbines have first power. On Hornsea 3, also, if you just take it from the top first, it is going really well on construction progress with a degree of completion of 30%, up from 25%. 43 monopiles installed. Second offshore converter station to be installed, first one already in. So sort of preparing for turbine installation in Q4 2026. It is a huge project, but it is going forward according to plan. Specifically regarding the reinforcement work at the Norwich Main Substation that we talked about before, very much in the last quarter.
Rasmus Errboe: We have now returned the vessel to Revolution, and it has now installed one of the remaining 5 turbines, so we are at 61. We expect to install the remaining in Revolution in the coming weeks and months. Therefore, also here, moving forward according to plan and the vast majority of the 65 turbines have first power. On Hornsea 3, also, if you just take it from the top first, it is going really well on construction progress with a degree of completion of 30%, up from 25%. 43 monopiles installed. Second offshore converter station to be installed, first one already in. So sort of preparing for turbine installation in Q4 2026. It is a huge project, but it is going forward according to plan. Specifically regarding the reinforcement work at the Norwich Main Substation that we talked about before, very much in the last quarter.
Speaker #1: So we are at 61. And then we expect to install the remaining in revolution in the coming weeks and months. So therefore, also here, moving forward according to plan and the vast majority of the 65 turbines have first power.
Speaker #1: On Hornsea 3, also, if you just take it from the top first, it's going really well on construction progress, with the degree of completion at 30%, up from 25%, and 43 monopiles installed.
Speaker #1: Second offshore converter station to be installed; first one already in. So, sort of preparing for turbine installation in the second in Q4 '26.
Speaker #1: It's a huge project. But it is going forward according to plan. Specifically regarding the reinforcement work at the Norwich main station that we talked about before, very much in the it's also moving forward according to plan.
Rasmus Errboe: It is also moving forward according to plan. We are working closely with the National Grid, and the expectation is that the back feed date will happen during September, which is also as we had planned. The risk has not gone away, obviously. We continue to stay very closely and work very closely together with National Grid. Based on what we have seen since we spoke last time, we have, as of now, a good feeling about the back feed date being reached as planned.
Rasmus Errboe: It is also moving forward according to plan. We are working closely with the National Grid, and the expectation is that the back feed date will happen during September, which is also as we had planned. The risk has not gone away, obviously. We continue to stay very closely and work very closely together with National Grid. Based on what we have seen since we spoke last time, we have, as of now, a good feeling about the back feed date being reached as planned.
Speaker #1: We are working closely with the National Grid. And the expectation is that the back feed date will happen during September, which is also as we had planned.
Speaker #1: The risk is not sort of the risk has not gone away, obviously. We continue to stay very closely and work very closely together with National Grid.
Speaker #1: But based on what we have seen since we spoke last time, we have, as of now, a good feeling about the back feed date being reached as planned.
Jenny Ping: Super helpful. Thank you very much.
Jenny Ping: Super helpful. Thank you very much.
Speaker #4: Super helpful. Thank you very much.
Operator: We have now a follow-up question from the line of Ahmed Farman from Jefferies. Please go ahead.
Operator: We have now a follow-up question from the line of Ahmed Farman from Jefferies. Please go ahead.
Speaker #2: We have now a follow-up question from the line of Ahmed Farman from Jefferies. Please go ahead.
Speaker #5: Yes, thank you. Thank you for taking a follow-up. Hopefully, a brief one. Just broadly, just at a high level, anything specific on the US policy around tariffs or any sort of section 2, 3, 2 related issues that are on your mind that could be for the second half of this year or is that a fairly sort of clear path right now?
Ahmed Farman: Yes. Thank you. Thank you for taking a follow-up, hopefully a brief one. Just broadly, just at a high level, anything specific on the US policy around tariffs or any sort of Section 232 related issues that are on your mind that could be for the second half of this year, or is that a fairly clear path right now? Thank you. I am obviously thinking more about Sunrise Wind. Thank you.
Ahmed Farman: Yes. Thank you. Thank you for taking a follow-up, hopefully a brief one. Just broadly, just at a high level, anything specific on the US policy around tariffs or any sort of Section 232 related issues that are on your mind that could be for the second half of this year, or is that a fairly clear path right now? Thank you. I am obviously thinking more about Sunrise Wind. Thank you.
Speaker #5: Thank you. I'm obviously thinking more about Sunrise wind. Thank you.
Rasmus Errboe: When it comes to the tariff updates, they did have a deadline or a timeline relative to beginning of August now. I believe it was the 8th. What we hear is that we would likely not hear anything or see anything on the 232 until at least September. We are uncertain on whether the tariffs. As of now, our preliminary evaluation relative to 50% tariffs on the parts that has been
Rasmus Errboe: When it comes to the tariff updates, they did have a deadline or a timeline relative to beginning of August now. I believe it was the 8th. What we hear is that we would likely not hear anything or see anything on the 232 until at least September. We are uncertain on whether the tariffs. As of now, our preliminary evaluation relative to 50% tariffs on the parts that has been
Speaker #1: When it comes to the tariff update, they did have a deadline or timeline relative to beginning of August now. I believe it was the 8th.
Speaker #1: What we hear is that we would likely not hear anything or see anything on the 2, 3, 2 until at least September. So we are unsure.
Speaker #1: Uncertain on whether the tariffs. So, as of now, our preliminary evaluation relative to if 50% tariffs on the parts—that has been sort of a part of the understanding for quite some time—is still in our estimates.
Trond Westlie: A part of the understanding for quite some time is still in our estimates. On other things on the US, no, nothing has moved ahead, so it has been quiet for a period.
Trond Westlie: A part of the understanding for quite some time is still in our estimates. On other things on the US, no, nothing has moved ahead, so it has been quiet for a period.
Speaker #1: On other things, on the US, no, nothing has moved ahead. So it has been sort of quiet for a period.
Speaker #5: Okay. Thank you.
Ahmed Farman: Okay, thank you.
Ahmed Farman: Okay, thank you.
Speaker #2: Ladies and gentlemen, that was the last question. I would now like to turn the conference back over to Rasmus Errboe for any closing remarks.
Operator: Ladies and gentlemen, that was the last question. I would now like to turn the conference back over to Rasmus Errboe for any closing remarks.
Operator: Ladies and gentlemen, that was the last question. I would now like to turn the conference back over to Rasmus Errboe for any closing remarks.
Speaker #1: Thank you all very much for joining, as always. We appreciate the interaction and the interest. If you have any further questions, please do not hesitate to ask.
Rasmus Errboe: Thank you all very much for joining. As always, we appreciate the interaction and the interest. If you have any further questions, please do not hesitate. Our IR team will be here to answer any one of them. Thank you. Stay safe and have a great day.
Rasmus Errboe: Thank you all very much for joining. As always, we appreciate the interaction and the interest. If you have any further questions, please do not hesitate. Our IR team will be here to answer any one of them. Thank you. Stay safe and have a great day.