Full Year 2026 Strike Energy Ltd Earnings Call
Speaker #1: Ellie Robertson, Managing Director and CEO, and it's lovely to have you here with us today. Before I get started, I'd like to introduce that we are lucky enough to have Julia Gruit joining us today.
Shelley Robertson: I'm Shelley Robertson, Managing Director and CEO, and it's lovely to have you here with us today. Before I get started, I'd like to introduce that we are lucky enough to have Julia Grdina joining us today. It's her first day in investor relations and corporate development role, and she'll be looking forward to engaging with you all as the year progresses. I thought I'd start today with just a reminder of who we are today at Strike. You all know Strike as a listed energy company, with a number of key projects that I'll work through today. We have a refreshed board since the end of the financial year, with Nev Power as Chair, Jill Hoffmann, Will Barker, and Stephen Bizzell joining me on the board. What we found is that a smaller, fit-for-purpose board is working really well for Strike.
Speaker #1: As her first day in Investor Relations and Corporate Development role, she'll be looking forward to engaging with you all as the year progresses.
Speaker #2: So I thought I'd start today with just a reminder of who we are today as Strike. You all know Strike as a listed energy company, and with a number of key projects that I'll work through today.
Speaker #2: We have a refreshed board since the end of the financial year, with NEV Power as chair, Jill Hofman will Barker and Steve Bissell joining me on the board.
Speaker #2: So what we found is that a smaller fit-for-purpose board is working really well for Strike, and we're enjoying moving the company forward as a group.
Shelley Robertson: We're enjoying moving the company forward as a group. This is just a brief overview of our portfolio for those of us perhaps who have joined in more recently onto the register. On the right, there's a map, and what you see in the blue there is our very extensive portfolio of more than 3,000 square kilometers of acreage in the Perth Basin. All that acreage is 100% owned by Strike, apart from the West Erregulla joint venture, which is 50/50 with Hancock Energy. Our key projects that I'll talk about today are Walyering, West Erregulla, and South Erregulla, as well as our exploration projects, Ocean Hill, Kadathinni, and the remainder of the Perth Basin.
Speaker #2: This is just a brief overview of our portfolio for those of us perhaps who have joined in more recently onto the register. On the right, there's a map, and what you see in the blue there is our very extensive portfolio of more than 3,000 square kilometers of acreage in the perth basin, and all that acreage is 100% owned by Strike, apart from the West Saragalla Joint Venture, which is 50/50 with Hancock Energy.
Speaker #2: So our key projects that I'll talk about today are Wellering, West Saragalla, and South Aragalla, as well as our exploration projects, Ocean Hill, Catacinni, and the remainder of the perth basin.
Speaker #2: So if we talk about the highlights of FY26 and recent milestones, certainly it's been an exciting year for Strike. FY26, with the continuing construction getting very close to commissioning of the South Aragalla Power project, which we call SEP.
Shelley Robertson: If we talk about the highlights of FY26 and recent milestones, certainly it's been an exciting year for Strike, FY26, with the continuing construction, getting very close to commissioning of the South Erregulla Peaking Power Plant, which we call SEPP. SEPP is an 85 megawatt power station based in the midwest, and we are very close to getting that power station online with Western Power in the final stages of commissioning and dynamic modeling. That's very exciting for us because it's been a big project on the go for a little while now. We also have West Erregulla, where we increased our net 2P reserves, and that's another exciting project I'll talk about. If you're on the recent webinar, you'll know, but we certainly reached agreement with Hancock on the way forward on a pathway to market for us, which is great.
Speaker #2: So SEP is an 85-megawatt power station based in the Midwest, and we are very close to getting that power station online with Western Power in the final stages of commissioning and dynamic modelling.
Speaker #2: So that's very exciting for us because it's been a big project on the go for a little while now. We also have West Aragalla, where we increased our net reserves, net GP reserves, and that's another exciting project I'll talk about.
Speaker #2: If you're on the recent webinar, you'll ll know, but we've certainly reached agreement with Hancock on the way forward on a pathway to market for us, which is great.
Speaker #2: And with Wellering, we'll talk through Wellering and where we're up to. And so here on here, we're also talking about the $30 million Macquarie facility that was made available when we reached agreement with Hancock on the implementation agreement.
Shelley Robertson: With Walyering, we'll talk through Walyering and where we're up to. On here, we're also talking about the AUD 30 million Macquarie facility that was made available when we reached agreement with Hancock on the implementation agreement. If we get through to our financial results now, we can talk to the sales revenue of AUD 62.8 million, the underlying EBITDA, AUD 17.6 million, and cash at 30 June, AUD 46.3 million. The important thing to note here is that we did have a big year with CapEx of AUD 151.3 million, which is predominantly for the South Erregulla Power Station. Acknowledging we had lower Walyering production, just with the natural field decline, but we've certainly done things to get that sorted out. That has meant increased third-party gas purchasing and sales during the year, which impacted our EBITDA.
Speaker #2: If we get through to our financial results now, so we can talk to the sales revenue of $62.8 million, the underlying EBITDA of $17.6 million, and cash at 30 June, $46.3 million.
Speaker #2: The important thing to note here is that we did have a big year with CapEx of $151.3, which is predominantly for the South Aragalla power station.
Speaker #2: Acknowledging we had lower Wellering production, just with the natural feel decline, but we've certainly done things to get that sorted out. But that has meant an increased third-party gas sort of purchasing and sales during the year, which impacted our EBITDA.
Speaker #2: What it has done, though, with our certainly with our investment has increased materially by around $59.1 million, with the advent of South Aragalla. If we talk to Wellering now, Wellering is the project that's been around for a little while, so it's been producing for a few years.
Shelley Robertson: What it has done, though, certainly our investment has increased materially by around AUD 59.1 million with the advent of South Erregulla. If we talk to Walyering now, Walyering is the project that's been around for a little while, so it's been producing for a few years. What we have seen is lower field production, so certainly reservoir decline. As a result of that, we've certainly had to do some interventions, which has included compression, bringing compression on, and purchasing third-party gas to meet our contractual commitments. I think the important thing here to note is that we are moving forward. We have put the compression online successfully and also drilled Walyering West, which has been a discovery and has given us a 21% increase in reserves there. So that's really important because it keeps that plant running into the future.
Speaker #2: What we have seen is lower field productions. So certainly reservoir decline, and as a result of that, we've certainly had to do some interventions, which has included compression, bringing compression on, and purchasing third-party gas to meet our contractual commitments.
Speaker #2: But I think the important thing here to note is that we are moving forward. We have put the compression online, successfully, and also drilled Wellering West, which has been a discovery and has given us a 21% increase in reserves there.
Speaker #2: So that's really important because it keeps that plant running into the future. We're currently working through the feed process on the way west well, and we'll keep you updated on that as we move forward.
Shelley Robertson: We're currently working through the FEED process on the Walyering West well, and we'll keep you updated on that as we move forward. What I would say is with compression online and Walyering West preparing to be tied in, Walyering is certainly looking better. South Erregulla, the power station, there's a lovely photo of it there. We're certainly very close now. The facility is amazing. It's 100% Strike-owned. We're running that power station from our own gas reserves. This is a very important project for us because it certainly for one, it demonstrates that we are able to bring a project online like this. This is the first gas reciprocating engine power station on the SWIS. It's new for WA, but it's very excitingly new for Strike as well, and the team have done an outstanding job in getting this project through to this point.
Speaker #2: So what I would say is with compression online and way west preparing to be tied in, Wellering is certainly looking better. South Aragalla, the power station, there's a lovely photo of it there.
Speaker #2: We're certainly very close now. The facility is amazing. It's 100% Strike owned, and we're running that power station from our own gas reserves. This is a very important project for us because it certainly for one, it demonstrates that we are able to bring a project online like this.
Speaker #2: This is the first gas reciprocating engine power station on the Swiss, and so it's new for WA, but it's very excitingly new for Strike as well.
Speaker #2: And the team have done an outstanding job in getting this project through to this point. What this project means for us is a new high-margin earnings strain for Strike, with exposure to both capacity credit payments and the electricity markets.
Shelley Robertson: What this project means for us is a new high-margin earnings stream for Strike, with exposure to both capacity credit payments and the electricity market. This slide gives you a little bit of a look at the capacity revenue that we look to be able to achieve through the power station once it's online. So for calendar year 2027, AUD 19 million in capacity revenue payments. Calendar year 2028, AUD 31 million. Calendar year 2029, up to AUD 42 million. With those capacity revenue payments, we actually get a 2-year firm look ahead on what the price is going to be, and at the moment, the prices are increasing, and so that's positive for us. In addition to these capacity revenue payments, we have the actual electricity sales. That revenue is driven by how many hours we are online.
Speaker #2: So this slide gives you a little bit of a look at the capacity revenue that we look to be able to achieve through the power station once it's online.
Speaker #2: So for calendar year 27, 19 million in capacity revenue payments, calendar year 28, 31 million and calendar year 29, up to 42 million. So with those capacity revenue payments, we actually get a two-year firm look ahead on what the price is going to be, and at the moment, the prices are increasing.
Speaker #2: And so that's positive for us. In addition to these capacity revenue payments, we have the actual electricity sales. So that revenue is driven by how many hours we are online.
Speaker #2: So how it will work at South Aragalla as a peaking plant is that we will look to optimise coming online when the wind is not blowing.
Shelley Robertson: How it will work at South Erregulla as a peaking plant is that we will look to optimize coming online when the wind is not blowing. When wind comes online, the price in the market drops, and we will stay out of the market. As the wind falls, South Erregulla will come online and begin generating. So we've got a very quick ramp-up time with the power station. We can come on as quickly as we like. The power is actually driven by 15-minute intervals, and so we'll be asked to come online based on the price that we've set. For example, there's a couple of revenue streams there for if we were producing 6 hours a day at a certain price or 10 hours a day at a certain price, we'll be certainly generating decent revenue.
Speaker #2: So when wind comes online, the price in the market drops, and it's we will stay out of the market, but as the wind falls, South Aragalla will come online, and begin generating.
Speaker #2: So we've got a very quick ramp-up time with the power station. We can come on as quickly as we like. The power is actually driven by 15-minute intervals, and so we'll be asked to come online based on the price that we've set.
Speaker #2: So for example, there's a couple of revenue streams there for if we were producing six hours a day at a certain price or 10 hours a day at a certain price we'll be certainly generating decent revenue.
Speaker #2: So although we've built some debt against this project to deliver, we certainly will have some too good revenue strains in SEP coming into play as we move forward.
Shelley Robertson: Although we have built some debt against this project to deliver, we certainly will have two good revenue streams from SEPP coming into play as we move forward. The other thing that is interesting about SEPP is its location. SEPP is located on Strike's 100% owned freehold land. We have 3,500 hectares of land in the midwest. You can see South Erregulla, the gas field there is just to the south of West Erregulla, the joint venture we have with Hancock. We have a connection through to the transmission network on a 132 kV line. We also have been running studies on that land area for some time now to understand wind generation. We have up to 300 megawatts of wind capacity there. It is quite a neat little project, which gives us lots of different opportunities.
Speaker #2: The other thing that's interesting about SEP is its location. So SEP is located on Strike, 100% owned, freehold land. So we have three and a half thousand hectares of land in the Midwest.
Speaker #2: And you can see South Aragalla, the gas field there is just to the south of West Aragalla, the joint venture we have with Hancock.
Speaker #2: We have a connection through to the transmission network on a 132 kV line, and we also have been running studies on that land area for some time now to understand wind generation.
Speaker #2: So we've got up to 300 megawatts of wind capacity there. So it's a quite a neat little project, which gives us lots of different opportunities.
Speaker #2: We're close to Perth, close to Geraldton, close to the Brand Highway where the fibre optic cables run. So a few different ideas coming through here, but lots of opportunity after this site.
Shelley Robertson: We are close to Geraldton, close to the Brand Highway, where the fiber optic cables run. A few different ideas coming through here, but lots of opportunity for this site. Moving on to West Erregulla. It was the big project that we announced on 31 August that we actually had reached agreement with Hancock on the pathway forward to putting our gas through their 100% owned Belisama gas processing facility. The Belisama gas processing facility is located just directly between South Erregulla and West Erregulla, and so just 3 kilometers from the West Erregulla field. Ultimately, it was a very good choice to choose that pathway for our gas, and we are now working very closely with Hancock to get our long-form documents completed before the end of this year.
Speaker #2: Moving on to West Aragalla, it was the big project that we announced on the 31st of August that we actually had reached agreement with Hancock on the pathway forward to putting our gas through their 100% owned Bella Pharma gas processing facility.
Speaker #2: So the Bella Pharma gas processing facility is located just directly between South Aragalla and West Aragalla, and so just three kilometres from the West Aragalla field.
Speaker #2: And so ultimately, it was a very good choice to choose that pathway for our gas, and we're now working very closely with Hancock to get our long-form documents completed before the end of this year.
Speaker #2: So here are some indicative revenue that we have from the West Aragalla facility. And from our field, at $8 a gigajoule is 127 million.
Shelley Robertson: Here is some indicative revenue that we have from the West Erregulla facility, and from our field at AUD 8 per gigajoule is AUD 127 million. We are targeting upstream FID by mid-FY28, which is the piece around the West Erregulla joint venture, the wells and so on. Then those wells will be connected through to the Belisama facility, targeting first gas by mid-calendar year 2029. Certainly, we have materially advanced our documents with Hancock over the past short period of time, and this is really one of Strike's biggest projects, biggest, most exciting projects. We are looking forward to getting this moving as quickly as we can. What we currently have with Hancock is we have the implementation agreement in place, which is the framework of all the key principles that help to guide our long-form document creation.
Speaker #2: So we're targeting upstream FID by mid-FY28, which is the piece around the West Aragalla joint venture, the Wells and so on. And then those Wells will be connected through to the Bella Pharma facility, targeting first gas by mid-calendar year 29.
Speaker #2: So certainly we have materially advanced our documents with Hancock over the past short period of time, and this is really one of Strike's biggest projects, biggest most exciting projects.
Speaker #2: So we're looking forward to getting this moving as quickly as we can. What we currently have with Hancock is we have the implementation agreement in place, which is the framework of all the key principles that help to guide our long-form document creation.
Speaker #2: So in those in that implementation agreement, a couple of things we have are a fixed capacity charge, which means we de-risk, we understand the cost of putting our gas through the Bella Pharma plant, and we then own that still own that gas out the other side to sell into the market.
Shelley Robertson: In that implementation agreement, a couple of things we have are a fixed capacity charge, which means we de-risk, we understand the cost of putting our gas through the Belisama plant, and we then still own that gas out the other side to sell into the market. We certainly are very aligned with Hancock on this development. We are looking forward to working closely with them to bring this project to market, because I think as we go forward, the gas market is tightening in Western Australia. There is going to be a bigger gap between supply and demand between about 2030. This gas is really materially important for the state of Western Australia. This is just a slide briefly outlining the Macquarie debt structure. It has been out in the domain previously, but I think it is just useful to understand.
Speaker #2: We certainly are very aligned with Hancock on this development. We're looking forward to working closely with them to bring this project to market because I think as we go forward, the gas market's tightening in Western Australia, there's going to be a bigger gap between supply and demand, between about 2030.
Speaker #2: So this gas is really materially important for the state of Western Australia. This is just a slide briefly outlining the Macquarie debt structure. So it's been out in the domain previously, but I think it's just useful to understand.
Speaker #2: We still have tranche C, which is uncommitted and subject to CPs on West Aragalla. So at the moment, our borrowings are 157.7 million, and that's predominantly on the Strike on the South Aragalla project.
Shelley Robertson: We still have Tranche C, which is uncommitted, and subject to CPs on West Erregulla. At the moment, our borrowings are AUD 157.7 million, and that's predominantly on the Strike, on the South Erregulla project. Our cash and net debt position is shown there as well. This is a slide that some of you will have been familiar with, and I've spoken to previously a couple of times. This really for us is the money slide. It shows our pipeline of growth. It's exciting for us. We have our foundation project, Walyering, with around AUD 52 million revenue per annum. Looking to backfill that production, the production decline with that Wayward well coming online fairly soon. Then we have South Erregulla, the power station. As soon as we get that commissioned by the end of this year, that's going to be real near-term cash flow.
Speaker #2: And our cash in net debt position is shown there as well. So this is a slide that some of you will have been familiar with, and I've spoken to previously a couple of times.
Speaker #2: But this really, for us, is the money slide. It shows our pipeline of growth. It's exciting for us. We have our foundation project, Waliaring, with around 52 million revenue per annum.
Speaker #2: And looking to backfill that production the production decline with that way West Well coming online fairly soon. Then we have South Aragalla, the power station.
Speaker #2: So as soon as we get that commissioned by the end of this year, that's going to be real near-term cash flow. So that's another how you look at it, but 50 to 75 million of revenue on top of Waliaring.
Shelley Robertson: That's another, how you look at it, but AUD 50 to 75 million of revenue on top of Walyering. Then West Erregulla coming online mid 2029 is very exciting. We've got a little bar chart there, which just shows illustrative gas prices and the revenue at that gas price of our 43.5 terajoules a day. The Belisama facility has a 210 TJ a day capacity, so our 43.5 TJ a day is a significant portion of that. Based on, say, an AUD 8 gas price, we're looking at a revenue stream there of AUD 127 million. When you add those three revenue streams together, we're starting to look at a significantly different Strike as we go forward. The fourth box there is around our exploration portfolio, and I know shareholders have been patiently waiting for some developments there around exploration and progress.
Speaker #2: And then West Aragalla coming online mid-29 is very exciting, and we've got a little bar chart there, which just shows illustrative gas prices and the revenue at that gas price of our 43.5 terajoules a day.
Speaker #2: So the Bella Pharma facility has a 210 TJ a day capacity. So our 43.5 TJs a day is a significant portion of that. And based on, say, an $8 gas price, we're looking at a revenue stream there of 127 million.
Speaker #2: So when you add those three revenue streams together, we're starting to look at a significantly different Strike as we go forward. The fourth box there is around our expiration portfolio and I know shareholders have been patiently waiting for some developments there around expiration and progress.
Speaker #2: So as we bring these cash flows online and we start generating some revenue paying down our debt, we're going to be very carefully managing capital, but we certainly have in our sights the importance of bringing on some of those expiration programs that we've all been waiting for.
Shelley Robertson: As we bring these cash flows online and we start generating some revenue, paying down our debt, we're going to be very carefully managing capital, but we certainly have in our sights the importance of bringing on some of those exploration programs that we've all been waiting for. Ocean Hill and Cattamarra are probably the first in the stack, and there are a number of others as well. It's a very exciting profile for us of Strike, and truly at a transformational point with Walyering already producing and giving us revenue. South Erregulla, really close. West Erregulla on the short-term horizon, and then our big exploration portfolio out the other side. I think we have enormous opportunity here at Strike to actually really capitalize on all of this and to deliver something really special.
Speaker #2: So Ocean Hill and Catacinia probably the first in the stack, and there are a number of others as well. So it's a very exciting profile for us of Strike.
Speaker #2: And truly, at a transformational point with Waliaring, already producing and giving us revenue, South Aragalla really close West Aragalla on the short-term horizon, and then our big expiration portfolio out the other side.
Speaker #2: So I think we have enormous opportunity here at Strike to actually really capitalise on all of this, and to deliver something really special. This is just a refresh on the expiration upside that we do have at Strike.
Shelley Robertson: This is just a refresh on the exploration upside that we do have at Strike. I spoke to Ocean Hill and Cattamarra, but in the middle there is L26, which is the West Erregulla footprint. The tenure we hold with Hancock also has near field upside. That will also be looked to be further exploration carried out in the coming years. The financial priorities for this year are obviously to get South Erregulla online, that's critical, and to actually convert that into cash flow. We're looking forward to that. Total forecast project cost is around AUD 186 million, and we're really looking like seeing that plant coming online by the end of this year.
Speaker #2: So I spoke to Ocean Hill and Catacinia, but in the middle there is L26, which is the West Aragalla footprint. So the 10-year we hold with Hancock also has Newfield upside.
Speaker #2: That will also be looked to be sort of further expiration carried out in the coming years. So the financial priorities for this year obviously to get South Aragalla online, that's critical, and to actually convert that into cash flow.
Speaker #2: So we're looking forward to that. Total forecast project cost was around 186 million, and we're really looking like seeing that plant coming online by the end of this year.
Speaker #2: Funding for West Aragalla to FID has been really important. So our agreement with Hancock saw us secure a $30 million in funding from Hancock to help us get through to FID, subject to Macquarie consent.
Shelley Robertson: Funding for West Erregulla to FID has been really important. Our agreement with Hancock saw us secure AUD 30 million in funding from Hancock to help us get through to FID subject to Macquarie consent. Certainly, that will help us to get through on West Erregulla. Then we have our debt facility with Macquarie. We got an additional facility released from Macquarie just recently, and that will actually help us to continue on all of our development fronts as well. Then around, I guess, the most important thing is us having real capital discipline to pursue exploration development programs throughout the coming year. This is the slide that I will end on. It is why Strike? Why now? I think everybody knows why Strike, why now. We have West Erregulla, Walyering, and South Erregulla all coming online. We have a really solid revenue growth ahead of us.
Speaker #2: But certainly, that will help us to get through on West Aragalla. Then we have our debt facility with Macquarie. So we've got an additional facility released from Macquarie just recently, and that will actually help us to sort of continue on all of our development fronts as well.
Speaker #2: And then around I guess the most important thing is us having real capital discipline to pursue expiration and development programs. Throughout the coming year.
Speaker #2: So this is the slide that I will end on. It's why Strike, why now. I think everybody knows why Strike, why now. We've got West Aragalla, Waliaring, and South Aragalla all coming online.
Speaker #2: We've got a really solid revenue growth ahead of us. And exposure to different markets. We've got the electricity market, we've got the gas market, which is great to have that diversification.
Shelley Robertson: Exposure to different markets. We have the electricity market, we have the gas market, which is great to have that diversification, and we also have the organic growth opportunities. I will speak again briefly about the opportunities we have at SEPP with that land we have and the location of that land and the opportunities that are around that as well. That is where I will end the presentation today, except we do have some questions that have come through, so I will just run through them now. The first one was just around, what will be happening with third-party gas sales as we go forward at Walyering. The idea is that now we have the Walyering compression installed, that we are expecting to be able to meet that contract for a longer period of time.
Speaker #2: And we also have the organic growth opportunities. And I'll speak again briefly about the opportunities we have at SEP. With that land, we have and the location of that land and the opportunities that are around that as well.
Speaker #2: So that is where I'll end the presentation today, except we do have some questions that have come through. So I'll just run through them now.
Speaker #2: The first one was just around what will be happening with third-party gas sales as we go forward at Waliaring. So the idea is that now we have the Waliaring compression installed.
Speaker #2: That we're expecting to be able to meet that contract for a longer period of time, and then in the background, we're working on the feed program to actually tie away way West back into the Waliaring facility.
Shelley Robertson: Then in the background, we are working on the FEED program to actually tie Walyering West back into the Walyering facility. So that we will be looking to minimize any third-party gas purchases in the future. I have just got some more questions that came through on email. The first question is, "What are the key work streams to be funded by the AUD 30 million Hancock pre-FID facility?" The upstream work program is expected to remain broadly consistent with the development scope previously communicated, including development drilling of West Erregulla 6 and completion activities, workovers of West Erregulla 2, 3, and 4. The detailed scope, sequencing, and budget for pre-FID work is currently being aligned with Hancock through the JV work program and budget process. We therefore do not intend to provide a more detailed work program or updated capital estimate until that is complete.
Speaker #2: So that will be looking to minimise any third-party gas purchases in the future. And I've just got some more questions that came through on email.
Speaker #2: So the first question is, what are the key work streams to be funded by the 30 million Hancock pre-FID facility? So the upstream work programs expected to remain broadly consistent with the development scope previously communicated, including development drilling of West Aragalla 6 and completion activities, work overs of West Aragalla's 2, 3, and 4.
Speaker #2: So the detailed scope, sequencing, and budget for pre-FID work is currently being aligned with Hancock through the JB work program and budget process. We therefore don't intend to provide a more detailed work program or updated capital estimate until that is complete.
Speaker #2: However, the 30 million of Hancock pre-FID. Is intended to support Strike's share of expenditure required to progress West Aragalla towards FID. While we currently expect the overall upstream work program to remain broadly consistent with those assumptions, made previously, Strike and Hancock are still aligned on the detailed work program and budget for the development.
Shelley Robertson: However, the AUD 30 million of Hancock pre-FID funding is intended to support Strike's share of expenditure required to progress West Erregulla towards FID. While we currently expect the overall upstream work program to remain broadly consistent with those assumptions made previously, Strike and Hancock are still aligned on the detailed work program and budget for the development. We are still working through that with Hancock. It is a little bit early to provide updated CapEx guidance at this stage. Importantly, Strike remains operator through to FID, which means we will be allowed to control the definition and optimization of the upstream development plan. By FID, we expect to have a more mature work program and sufficiently defined CapEx estimate to provide updated guidance. I hope that answers that question.
Speaker #2: So we're still working through that with Hancock. So it's a little bit early to provide updated CAPEX guidance at this stage. Importantly, Strike remains operator through to FID, which means we'll be allowed to control the definition and optimisation of the upstream development plan.
Speaker #2: By FID, we expect to have a more mature work program and sufficiently deep defined CAPEX estimate to provide updated guidance. So I hope that answers that question.
Speaker #2: The next question is, what guidance are you giving on remaining upstream CAPEX at West Aragalla? Oh, actually, I've answered that one now. So then what's the remaining CAPEX for South Aragalla as that's 30 June 2026?
Shelley Robertson: The next question is, "What guidance are you giving on remaining upstream CapEx at West Erregulla?" Oh, actually, I've answered that one now. "What's the remaining CapEx for South Erregulla as at 30 June 2026?" As at 30 June 2026, Strike forecasts approximately AUD 16 million of remaining CapEx to complete South Erregulla. Since year-end, the project has continued to progress and remains forecast expenditure is now approximately AUD 11 million. As with any project nearing completion and commissioning, the remaining expenditure is forecast to remain subject to final commissioning activities, project closeout, and the additional works that may be required. "What's the use of funds for the drawdown of the AUD 30 million Macquarie facility in December?
Speaker #2: As that's 30 June 2026, Strike forecasts approximately 16 million of remaining CAPEX to complete South Aragalla. Since year-end, the project has continued to progress and remains forecast expenditure is now approximately 11 million.
Speaker #2: As with any project nearing completion and commissioning, the remaining expenditure is forecast to remain subject to final commissioning activities. Project closeout and the additional works that may be required.
Speaker #2: So what's the use of funds for the drawdown of the 30 mil Macquarie facility in December? Is this for South Aragalla works, or will it sit on the balance sheet for now?
Shelley Robertson: Is this for South Erregulla works, or will it sit on the balance sheet for now?" The AUD 30 million Macquarie facility was drawn to provide additional liquidity as Strike completes South Erregulla and progresses its broader development program. The funds are not specifically quarantined to South Erregulla and will be deployed against the company's funding requirements as they arise. In the interim, any funds not immediately required will remain as cash on the balance sheet. I think that's all the questions that we have today. If there are any additional questions, please feel free to send them through to myself or Julia. We'll make sure that Julia's email address is available for any of you that would like to reach out.
Speaker #2: The 30 million Macquarie facility was drawn to provide additional liquidity as Strike completes South Aragalla and progresses its broader development program. The funds are not specifically quarantined to South Aragalla and will be deployed against the company's funding requirements, as they arise.
Speaker #2: In the interim, any funds not immediately required will remain as cash on the balance sheet. So I think that's all the questions that we have today.
Speaker #2: So if there are any additional questions, please feel free to send them through to myself or Julia. We'll make sure that Julia's email address is available for any of you that would like to reach out.
Speaker #2: I'm very pleased to have Julia on the team, and we'll be looking forward to getting out and meeting some more of the shareholders in the coming weeks and months.
Shelley Robertson: I'm very pleased to have Julia on the team, and we'll be looking forward to getting out and meeting some more of the shareholders in the coming weeks and months. Thank you very much for joining us on the webinar today. Like I said, if you have any questions, please do send them through. Thank you.
Speaker #2: So thank you very much for joining us on the webinar today. Like I said, if you have any questions, please do send them through.
More STX earnings call transcripts
- STX - Q1 2026 Seagate Technology Holdings PLC Earnings Call (October 28, 2025)
- STX - Q2 2026 Seagate Technology Holdings PLC Earnings Call (January 27, 2026)
- STX - Q3 2026 Seagate Technology Holdings PLC Earnings Call (April 28, 2026)
- STX - Q4 2026 Seagate Technology Holdings PLC Earnings Call (July 28, 2026)