How Much New Power Capacity Does a Customer Contract Support?

Two Constellation contracts cover 866 MW and support 220 MW of planned additions. Its Crane restart shows how to check a separate question about delivery.

In this article

Constellation disclosed power contracts with Walmart and Amazon totaling 866 megawatts. The associated plant expansions total 220 MW. For an analyst forecasting how much generation the company will add, entering the two contracts at face value would overstate the planned addition by 646 MW. The contracts also support existing plants. Constellation’s September 2026 Form 10-Q identifies the two amounts separately for each site. Constellation’s long-term nuclear power purchase agreements

Count the expansion at each plant

Site and customerCapacity covered by power purchase agreementPlanned capacity increaseIncremental MW as a share of contract MW
Dresden, Walmart176 MW30 MW17.0%
Calvert Cliffs, Amazon690 MW190 MW27.5%
Both sites866 MW220 MW25.4%

We divided the planned increase by the contract amount in each row. The combined 25.4% describes the scope of the two agreements. It gives neither the probability of completion nor how often the plants will generate electricity. Constellation expected the Calvert Cliffs expansion to come online between 2030 and 2032. Applying 690 MW to the first year in the model would make two errors at once, in the size of the expansion and its timing. Third-quarter filing, “Long-Term Nuclear PPAs”

A portfolio roll-up can introduce a third error. Constellation’s second-quarter group of agreements covered 920 MW. The company explicitly included the 176 MW Walmart agreement in that figure. A model that records both the group and its components must mark that relationship before summing the rows. The filing describes the September Amazon agreement separately.

A signed buyer and a regulatory decision answer different questions

At the Crane Clean Energy Center in Pennsylvania, the proposed addition comes from returning a previously closed plant to service. Constellation identified about 835 MW and signed a 20-year contract for Microsoft to buy energy from the restarted plant. That establishes an identified buyer. The announcement describes matching Microsoft’s regional data-center electricity use with carbon-free energy. It supplies neither a site-specific consumption figure for a Microsoft data center nor a price per megawatt-hour. Constellation’s Crane announcement

Three records change how those megawatts belong in a forecast.

Public recordWhat the analyst can enter
Constellation’s signed purchase agreementCustomer and 20-year term. Delivery depends on the plant returning to service.
September 25, 2026 NRC environmental findingThe regulator completed its environmental assessment of the proposed licensing actions and found no significant environmental impact. The agency was still considering an exemption and three license amendments to support a restart. Granting them and starting commercial generation are separate events.
Constellation’s third-quarter regulatory noteFERC granted a waiver in June and Constellation transferred capacity interconnection rights to Crane. Record that grid milestone separately from permission to operate and the first sale of electricity.

The September notice identifies the facility by its former name, Three Mile Island Unit 1, as well as Crane. Matching both names avoids treating the restarted unit as a second project. The initial grid study had identified contingent upgrades with some projected in-service dates as late as December 2030. Constellation sought the transfer to reduce the number of upgrades needed for full deliverability. Neither the old study date nor the June waiver supplies a commercial start date. NRC’s final environmental finding · Constellation’s regulatory note 3

What would move the project into operating capacity?

In the same filing Constellation used different language for Pin Oak Creek. The company reported that the 460 MW facility achieved commercial operation in April 2026. That disclosure supports transferring the plant from a project schedule to an operating-capacity schedule. Its April start still leaves a partial year, and a peaking plant’s capacity does not tell an analyst how many megawatt-hours it sold. Constellation’s project updates, “Pin Oak Creek Energy Center”

The practical model change is to carry a separate row for the customer agreement, the incremental plant capacity and the date commercial operation begins. A permit can change the timing assumption without changing the number of MW. A larger customer agreement can change contracted sales without adding a single MW. Our buyer’s guide to company and sector research tools covers how to revisit that judgment when a new disclosure arrives.